us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week

Written on: October 20th, 2017 in US 301 Project UpdatesUS301

Monday, October 23, 2017 through Thursday, October 26, 2017 Continue bridge construction activities on Boyd’s Corner Road (SR 896). Motorists should anticipate an eastbound or westbound lane closure on Boyds Corner Road (SR 896) west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for the US 301 Mainline Project for the week of October 16.

Written on: October 13th, 2017 in US 301 Project UpdatesUS301

Monday, October 16 through Thursday, October 19 Continue bridge construction activities on Boyd’s Corner Road (SR 896). Motorists should anticipate an eastbound or westbound lane closure on Boyds Corner Road (SR 896) west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9 a.m. until 3 […]


Read More

sr141

SR141/I-95 Ramp Interchange Project

Written on: October 12th, 2017 in SR141

SR141/I95 Ramp Improvement Project October 9, 2017 The contractor, Mumford & Miller Inc., have begun to clear vegetation and widening the roadway on SR141 southbound on the closed side of the roadway. They are demolishing the existing SR141 southbound and northbound bridges, constructing foundations and building piers for the new bridges. They have also begun […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for the week of October 9 for the US 301 Mainline Project.

Written on: October 5th, 2017 in US 301 Project UpdatesUS301

Monday, October 9 through Thursday, October 12 Continue bridge construction activities on Boyd’s Corner Road (SR 896). Motorists should anticipate an eastbound or westbound lane closure on Boyds Corner Road (SR 896) west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9 a.m. until 3 […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for the week of October 2 on the US 301 Mainline Project.

Written on: September 29th, 2017 in US 301 Project UpdatesUS301

Monday, October 2 through Thursday, October 5 Continue bridge construction activities on existing US 301. Motorists should anticipate a northbound or southbound lane closure on US 301 at Strawberry Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9 a.m. until 3 p.m. Continue bridge construction activities on […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week.

Written on: September 22nd, 2017 in US 301 Project UpdatesUS301

Monday, September 25, 2017 through Thursday, September 28, 2017 Continue bridge construction activities on existing US 301. Motorists should anticipate a northbound or southbound lane closure on US 301 at Strawberry Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m. Continue bridge construction […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week.

Written on: September 15th, 2017 in US 301 Project UpdatesUS301

Monday, September 18, 2017 through Thursday, September 21, 2017 Continue bridge construction activities on existing US 301. Motorists should anticipate a northbound or southbound lane closure on US 301 at Strawberry Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m. Continue bridge construction […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week.

Written on: September 8th, 2017 in US 301 Project UpdatesUS301

Monday, September 11, 2017 through Thursday, September 14, 2017 Continue bridge construction activities on Boyd’s Corner Road (SR 896). Motorists anticipate an eastbound or westbound lane closure on Boyds Corner Road (SR 896) west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the week of September 5.

Written on: September 1st, 2017 in US 301 Project UpdatesUS301

Tuesday, September 5 through Thursday, September 7 Continue bridge construction activities on Boyd’s Corner Road (SR 896). Motorists anticipate an eastbound or westbound lane closure on Boyds Corner Road (SR 896) west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9 a.m. until 3 p.m. […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week.

Written on: August 25th, 2017 in US 301 Project UpdatesUS301

Monday, August 28, 2017 through Thursday, August 31, 2017 Continue bridge construction activities on Boyd’s Corner Road (SR 896). Motorists anticipate an eastbound or westbound lane closure on Boyds Corner Road (SR 896) west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to […]


Read More


+