sr141

SR141/I-95 Ramp Interchange Project

Written on: October 22nd, 2018 in SR141

Delaware Department of Transportation
Traffic Alert – For Immediate Release
Office of Community Relations
Contact: Bud Freel, New Castle County Legislative Liaison
Phone: (302) 577-5100
Cell Phone: (302) 547-6215

SR 141/I-95 Interchange Project Will Require Nighttime Lane and Ramp Closure for Milling and Paving
WHEN: 8 PM until 5 AM on Sunday, October 21, 2018 through Thursday, October 25, 2018
In the event of inclement weather, the lane and ramp closures will occur at 9 PM on Friday, October 26, 2018 until 8 AM on Saturday, October 27, 2018
WHERE: I-295 Northbound to I-95 Northbound between Exit 5 and past SR 141 Northbound Interchange AND Closure of Exit 2/SR 141 Southbound to I-295 Northbound.
WHAT: DelDOT’s announces to motorists that there will be lanes closed with a shifting of traffic on I-295 northbound to I-95 northbound and the closure of the ramp for milling and paving.
Detour: Motorists traveling on SR 141 southbound will follow detour signs to westbound Commons Boulevard, right onto Churchmans Road, enter onto SR 1 southbound and merge to I-95 northbound.
Detour signage will be posted for motorists.

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week.

Written on: October 19th, 2018 in US 301 Project UpdatesUS301

Monday, October 22, 2018 through Thursday October 25, 2018 – Dayshift Continue bridge construction activities along SR 1. Motorists should anticipate a single left or right lane closure along northbound and southbound SR 1 between the Biddles Toll Plaza and the Roth Bridge from 7:00 a.m. to 3:00 p.m. Continue roadway widening activities along southbound […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction for the US 301 Mainline Project during the week of October 15, 2018.

Written on: October 12th, 2018 in US 301 Project UpdatesUS301

Monday, October 15, 2018 through Thursday October 18, 2018: Dayshift Continue bridge construction activities along SR 1. Motorists should anticipate a single left or right lane closure along northbound and southbound SR 1 between the Biddles Toll Plaza and the Roth Bridge from 7 AM until 3 PM. Bridge widening construction activities along SR 1 […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week.

Written on: October 5th, 2018 in US 301 Project UpdatesUS301

Tuesday, October 9, 2018 through Thursday October 11, 2018 – Dayshift Continue bridge construction activities along SR 1. Motorists should anticipate a single left or right lane closure along northbound and southbound SR 1 between the Biddles Toll Plaza and the Roth Bridge from 7:00 a.m. to 3:00 p.m. Bridge widening construction activities along SR […]


Read More

sr141

SR141/I-95 Ramp Interchange Project

Written on: October 2nd, 2018 in SR141

SR141/I-95 Ramp Improvement Project October 1, 2018 The contractor, Mumford & Miller Inc., continue to pave SR141 northbound and southbound. They are building fences for the new SR141 northbound and southbound bridges. They continue to construct the Exit 5 ramp from I295 northbound to SR141 northbound. They are working on installing utility infrastructure and large […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule for the US 301 Mainline Project during the week of October 1, 2018.

Written on: September 28th, 2018 in US 301 Project UpdatesUS301

Monday, October 1, 2018 through Thursday October 4, 2018: Dayshift Continue bridge construction activities along SR 1. Motorists should anticipate a single left or right lane closure along northbound and southbound SR 1 between the Biddles Toll Plaza and the Roth Bridge from 7 AM until 3 PM. Bridge widening construction activities along SR 1 […]


Read More

sr141

SR141/I-95 Ramp Interchange Project

Written on: September 24th, 2018 in SR141

SR141/I-95 Ramp Improvement Project September 24, 2018 The contractor, Mumford & Miller Inc., continue to pave SR141 northbound and southbound. They are building fences and parapets for the new SR141 northbound and southbound bridges. They continue to construct the Exit 5 ramp from I295 northbound to SR141 northbound. They are working on installing utility infrastructure […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction for the US 301 Mainline Project – Week of September 24, 2018.

Written on: September 21st, 2018 in US 301 Project UpdatesUS301

Monday, September 24, 2018 through Thursday September 27, 2018: Dayshift Continue bridge construction activities along SR 1. Motorists should anticipate a single left or right lane closure along northbound and southbound SR 1 between the Biddles Toll Plaza and the Roth Bridge from 7 AM until 3 PM. Bridge widening construction activities along SR 1 […]


Read More

sr141

SR141/I-95 Ramp Interchange Project

Written on: September 17th, 2018 in SR141

SR141/I-95 Ramp Improvement Project September 17, 2018 The contractor, Mumford & Miller Inc., continue to pave SR141 northbound and southbound. They are building fences and parapets for the new SR141 northbound and southbound bridges. They continue to construct the Exit 5 ramp from I295 northbound to SR141 northbound. They are working on installing utility infrastructure […]


Read More

us-301-project-updates

Below is an outline of the US 301 Mainline Project construction for the week of September 17, 2018.

Written on: September 14th, 2018 in US 301 Project UpdatesUS301

Monday, September 17, 2018 through Thursday September 20, 2018: Dayshift Continue bridge construction activities along SR 1. Motorists should anticipate a single left or right lane closure along northbound and southbound SR 1 between the Biddles Toll Plaza and the Roth Bridge from 7 AM until 3 PM. Bridge widening construction activities along SR 1 […]


Read More


+