Written on: January 10th, 2014 in Route 26
DelDOT contractor, George & Lynch, is scheduled to begin the Route 26 roadway widening project on Monday, Jan 13.
This is the anticipated schedule of activities and lane closures during the Route 26 project, Jan. 13 through Jan. 24:
Jan. 13 through Jan. 17:
George & Lynch will be clearing and grubbing the south side of Route 26, from Powell Farm Road to Route 17 (Roxana Road). No lane closures are expected.
Jan. 21 through Jan. 24.
George & Lynch will be clearing and grubbing the south side of Route 26, from Powell Farm Road to Route 17 (Roxana Road) Expect the eastbound road to be close.
We will continue to provide updates on upcoming work on Route 26 as information becomes available. As always, we thank you for your patience.