Route 54 Project – Updates

Written on: May 11th, 2012 in Route 54

It was a very productive week on the Route 54 construction project this past week, as crews were able to complete the final lift of asphalt, completing the mainline and several turn lanes. On Sunday, May 6 and Monday May 7, crews paved both the eastbound and westbound lanes of the project including all through […]


Read More

route-54

Route 54 Project Update

Written on: May 4th, 2012 in Route 54

DelDOT wishes to note that there was an unexpected lane closure to allow for the installation of a pipe at the east end of the job.  That lane closure should be pulled up by 2pm at the latest.   DelDOT appreciates hearing from business owners about this issue, and will handle it accordingly with the contractor.  […]


Read More

route-54

Route 54 Project – Updates

Written on: May 3rd, 2012 in Route 54

May 3, 2012 – Progress continued on the Route 54 construction project this past week, as crews were able to complete the second lift of asphalt.  We wanted to start the final lift of pavement this week as well, but intermittent showers made the operation tentative.  We typically will not start paving the surface course […]


Read More

elkton-road

Elkton Road Construction – Updates

Written on: April 30th, 2012 in Elkton Road

Greggo & Ferrara will continue to grade for curb and sidewalk followed by placement of curb and sidewalk from Lincoln Dr to Veterans Dr with flagger controlled intermittent lane closures. Drainage pipe installation will continue on Apple Rd followed by Verizon underground duct relocation; this work is behind the PCC barrier placed for the southbound Apple Rd closure. Intersection reconstruction […]


Read More

route-54

Route 54 Project – Updates

Written on: April 27th, 2012 in Route 54

April 26, 2012 – DelDOT is making good progress on the Route 54 construction project, despite a few rain days during the week of April 18-April 26.  The contractor is continuing to work on installing the three lifts of asphalt pavement. On the north side of the project, the first lift has been completed, and […]


Read More

route-54

Route 54 Project – Updates

Written on: April 25th, 2012 in Route 54

April 13, 2012 –  DelDOT will perform weekend work on April 14 and April 15 . This work is to perform paving operations and will require daytime lane restrictions on April 14 and 15.  DelDOT will be working in earnest to complete as much work as possible before the Memorial Day holiday weekend. Also, DelDOT […]


Read More

elkton-road

Elkton Road Project Update

Written on: April 17th, 2012 in Elkton Road

Road excavation and GABC stone base placement will occur between Lincoln Dr and Veterans Dr with flagger controlled intermittent lane closures, as needed. Drainage pipe installation will continue between Veterans Dr and Apple Rd with intermittent lane closures. Fine grading of GABC stone base will occur between Casho Mill Rd and Lincoln Dr, no lane […]


Read More

route-54

Route 54 Project – Updates

Written on: April 4th, 2012 in Route 54

As of March 26 the Contractor has added an additional crew resulting in a total of 3 crews.  The crews are performing excavation of the existing roadway, minor drainage and placement/grading of stone base course for asphalt, curb and sidewalk.  In addition to the 3 crews for the general contractor there is 1 crew for […]


Read More

route-54

Route 54 Project – Updates

Written on: March 30th, 2012 in Route 54

Presently, the contractor has completed the excavation on the north side of the road and is completing the placement of the stone base.  The contractor has also begun the placement of the curb.  In the next few weeks, the contractor is hoping to begin placing the sidewalk and asphalt for the north side widening.  Presently, […]


Read More

i95sr1-interchange

I-95/SR 1 Interchange Project – Update

Written on: January 25th, 2012 in I95/SR1 Interchange

Christiana Mall Road Bridge: All three deck pours are complete.  This week the contractor will be preparing for the parapet wall construction.  The goal is to open the new bridge to traffic in mid to late March, but that date is very weather dependent. For more information, please visit the project website at i95.deldot.gov.


Read More


+