DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

route-54

Route 54 Project – Updates

Written on: March 30th, 2012 in Route 54

Presently, the contractor has completed the excavation on the north side of the road and is completing the placement of the stone base.  The contractor has also begun the placement of the curb.  In the next few weeks, the contractor is hoping to begin placing the sidewalk and asphalt for the north side widening.  Presently, the schedule shows a completion in Summer 2012, but the contractor is continuously looking for opportunities to achieve an earlier completion.  Any work performed beyond the Memorial Day holiday will be done so in a manner to create minimal impacts to the summer traffic.

For more information, please visit the project page.




+