Written on: November 23rd, 2016 in US 301 Project Updates, US301
Tuesday, November 29, 2016 through Saturday, December 3, 2016 Begin hauling activities Summit Bridge Road at night. Motorists should anticipate the following nightly closures of Summit Bridge Road: • Monday night, November 28, from 8:00 p.m. through 5:00 a.m. • Tuesday night, November 29, from 8:00 p.m. through 5:00 a.m. • Wednesday night, November 30, […]
Written on: November 18th, 2016 in US 301 Project Updates, US301
Sunday, November 20, 2016 through Tuesday, November 22, 2016 Begin setting temporary concrete barrier on Summit Bridge Road, north of Armstrong Corner Road on Sunday, November 20, 2016. Motorists should anticipate a southbound lane closure on Summit Bridge Road, north of Armstrong Corner Road with traffic alternating through the work zone utilizing a flagging operation […]
Written on: November 15th, 2016 in SR141
SR141/I-95 Ramp Interchange Project November 4, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will place fill for the widening of ramps from SR141 southbound to I-95 northbound and constructing the side slopes of southbound SR141. LANE CLOSURES: Motorists should expect […]
Written on: November 13th, 2016 in US 301 Project Updates, US301
Monday, November 14, 2016 through Friday, November 18, 2016 Motorists should anticipate northbound and southbound lane shifts on Summit Bridge Road, north of Armstrong Corner Road, with traffic with both lanes getting through the work zone daily. Continue installing roadway drainage pipes across existing northbound U.S. Route 301 between Strawberry Lane and the Maryland Line. […]
Written on: November 4th, 2016 in SR141
SR141/I-95 Ramp Interchange Project November 4, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will place fill for the widening of ramps from SR141 southbound to I-95 northbound and constructing the side slopes of southbound SR141. LANE CLOSURES: Motorists should expect […]
Written on: November 4th, 2016 in US 301 Project Updates, US301
Monday, November 6, 2016 through Friday, November 11, 2016 Motorists should anticipate northbound and southbound lane shifts on Summit Bridge Road, north of Armstrong Corner Road, with traffic with both lanes getting through the work zone daily. Continue installing roadway drainage pipes across existing northbound U.S. Route 301 between Strawberry Lane and the Maryland Line. […]
Written on: October 27th, 2016 in US 301 Project Updates, US301
Monday, October 31, 2016 through Friday, November 4, 2016 Begin installation of Temporary Concrete Barrier wall on Summit Bridge Road, north of Armstrong Corner Road. Motorists should anticipate northbound and southbound lane closures on Summit Bridge Road, north of Armstrong Corner Road, with traffic alternating through the work zone utilizing a flagging operation by construction […]
Written on: October 25th, 2016 in SR141
SR141/I-95 Ramp Interchange Project October 21, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will continue to place fill for the widening of ramps from SR141 northbound and southbound to I-95 northbound and constructing the side slopes of southbound SR141. On […]
Written on: October 25th, 2016 in SR141
SR141/I-95 Ramp Interchange Project October 14, 2016 The contractor, Mumford & Miller Inc., has completed driving piles on one side of both southbound and northbound SR141. They are constructing the concrete structures for the new bridges on SR141. This week, the contractor will continue to place fill for the widening of ramps from SR141 northbound […]
Written on: October 25th, 2016 in SR141
SR141/I-95 Ramp Interchange Project October 7, 2016 The contractor, Mumford & Miller Inc., has completed driving piles on one side of both southbound and northbound SR141. They are constructing the concrete structures for the new bridges on SR141. This week, the contractor will continue to place fill for the widening of ramps from SR141 northbound […]