Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: November 18th, 2016 in US 301 Project Updates US301

Sunday, November 20, 2016 through Tuesday, November 22, 2016

Begin setting temporary concrete barrier on Summit Bridge Road, north of Armstrong Corner Road on Sunday, November 20, 2016. Motorists should anticipate a southbound lane closure on Summit Bridge Road, north of Armstrong Corner Road with traffic alternating through the work zone utilizing a flagging operation by Law Enforcement and construction personnel from 5:00 p.m. to 5:00 a.m.

Motorists should anticipate northbound and southbound lane shifts on Summit Bridge Road, north of Armstrong Corner Road, with traffic with both lanes getting through the work zone daily.

Begin removing temporary concrete traffic barrier along northbound Route 13. Motorists should anticipate single lane closures on northbound Route 13 between Port Penn Road and Old Hyetts Corner Road from 9:00 a.m. to 3:00 p.m.

Begin setting temporary concrete barrier along southbound SR 1 between the Roth Bridge and the Biddles Toll Plaza. Motorists should anticipate a right lane closure on southbound State Route 1 between the Roth Bridge and the Biddles Toll Plaza from 6:00 p.m. to 6:00 a.m.

Continue pile driving activities in the median of Route 1, north of the toll plaza. No lane closures are anticipated for this activity.

Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00 a.m. to 5:00 p.m.

Continue dirt hauling activities on Boyds Corner Road. Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road west of Jamison Corner Road from 8:00 a.m. to 4:00 p.m.

Continue dirt hauling activities across Armstrong Corner Road. Motorists should anticipate a flagging operation by construction personnel on Armstrong Corner Road west of Summit Bridge Road from 7:00 a.m. to 5:00 p.m.

Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7:00 a.m. to 5:00 p.m.

Middle Neck Roads is closed at U.S. Route 301 and will remain closed until the end of December of 2016. Motorists wishing to access Middle Neck Road from U.S. Route 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.