Written on: January 9th, 2017 in US 301 Project Updates, US301
Tuesday, January 10, 2017 through Thursday, January 12, 2017 Continue bridge construction activities along State Route 1. Motorists should anticipate a left lane closure along northbound or southbound State Route 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m. Monday, January 9, 2017 through Friday, January 13, 2017 Continue installing […]
Written on: January 5th, 2017 in SR141
SR141/I-95 Ramp Interchange Project January 3, 2017 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. The contractor will continue to place fill for the widening of SR141 southbound and northbound to I-95. Beam installation will take place on SR141 southbound and the placement of storm drains […]
Written on: January 5th, 2017 in SR141
SR141/I-95 Ramp Interchange Project December 23, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. The contractor will continue to place fill for the widening of SR141 southbound and northbound to I-95. Beam installation will take place on SR141 southbound and the placement of storm drains […]
Written on: January 5th, 2017 in SR141
SR141/I-95 Ramp Interchange Project December 16, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. The contractor will continue to place fill for the widening of SR141 southbound and northbound to I-95. This week, beam installation will begin on SR141 southbound and the placement of storm […]
Written on: December 29th, 2016 in US 301 Project Updates, US301
Continue bridge construction activities along SR 1. Motorists should anticipate a left lane closure along northbound or southbound SR 1 between the Roth Bridge and Toll Plaza from 9 a.m. until 3 p.m. Tuesday, January 3 through Friday, January 6 Continue installing ITMS along the right shoulder of northbound U.S. Route 13. Motorists should anticipate […]
Written on: December 23rd, 2016 in US 301 Project Updates, US301
Continue bridge construction activities along SR 1. Motorists should anticipate a left lane closure along southbound SR 1 between the Roth Bridge and Toll Plaza. Tuesday, December 27 through Friday, December 30 Continue installing ITMS along the right shoulder of northbound U.S. Route 13. Motorists should anticipate a right shoulder closure along northbound U.S. Route […]
Written on: December 16th, 2016 in US 301 Project Updates, US301
Sunday, December 18, 2016 through Friday, December 23, 2016 Strawberry Lane will be closed to traffic at U.S. Route 301 on December 19, 2016 and remain closed until approximately December 2017. Motorists wanting to access the east side of Strawberry Lane from U.S. Route 301 will follow Levels Road (SR 15) to Strawberry Lane. Motorists […]
Written on: December 13th, 2016 in SR141
SR141/I-95 Ramp Interchange Project December 2, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will place fill for the widening of SR141 southbound and northbound to I-95. LANE CLOSURES: Motorists should expect traffic on SR141 northbound and southbound to be reduced […]
Written on: December 13th, 2016 in SR141
SR141/I-95 Ramp Interchange Project November 18, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will place fill for the widening of SR141 southbound and northbound to I-95. LANE CLOSURES: Motorists should expect traffic on SR141 northbound and southbound to be reduced […]
Written on: December 9th, 2016 in US 301 Project Updates, US301
Sunday, December 11, 2016 through Saturday, December 17, 2016 Begin placing concrete for new bridge pier along southbound State Route 1. Motorists should anticipate single lane closures on southbound State Route 1 between the Roth Bridge and the Toll Plaza from 9 a.m. to 3:00 p.m. Continue removing existing pipe culvert along Port Penn Road, […]