DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week.

Written on: June 30th, 2017 in US 301 Project UpdatesUS301

Thursday, July 6, 2017 Continue bridge construction activities on Boyd’s Corner Road (SR 896). Motorists should anticipate an eastbound or westbound lane closure on Boyds Corner Road (SR 896) west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m. Continue excavation […]


Read More

sr141

141/95 Ramp Interchange Project

Written on: June 27th, 2017 in SR141

SR141/I-95 Ramp Interchange Project June 26, 2017 The contractor, Mumford & Miller Inc., will continue placing fill for widening I-95 northbound acceleration lane from SR 141. They will continue to form and pour barrier for SR 141 northbound. They are working on installing utility infrastructure and constructing overhead sign structures through the SR 141 and […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the week of June 26.

Written on: June 23rd, 2017 in US 301 Project UpdatesUS301

Monday, June 26 through Thursday, June 29 Continue bridge construction activities on Boyd’s Corner Road (SR 896). Motorists should anticipate an eastbound or westbound lane closure on Boyds Corner Road (SR 896) west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9 a.m. until 3 […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week.

Written on: June 16th, 2017 in US 301 Project UpdatesUS301

Monday, June 19, 2017 through Thursday, June 22, 2017 Continue bridge construction activities on Boyd’s Corner Road (SR 896). Motorists should anticipate an eastbound or westbound lane closure on Boyds Corner Road (SR 896) west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for the US 301 Mainline Project for the week of June 12.

Written on: June 9th, 2017 in US 301 Project UpdatesUS301

Monday, June 12 through Thursday, June 15 Relocate temporary concrete barrier wall along US Route 13, south of the on ramp to State Route 1. Motorists should anticipate single left lane or right lane closures on northbound and southbound US 13 between Port Penn Road and the on ramp for State Route 1 from 9 […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week.

Written on: June 2nd, 2017 in US 301 Project UpdatesUS301

Monday, June 5, 2017 through Thursday, June 8, 2017 Continue repainting of temporary concrete barrier wall along US 13, south of the on ramp to State 1. Motorists should anticipate single left lane or right lane closures on northbound and southbound US 13 between Port Penn Road and the on ramp for SR 1 from […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project for the week of May 30.

Written on: May 25th, 2017 in US 301 Project UpdatesUS301

Tuesday, May 30 through Thursday, June 1- Nightshift Continue bridge construction for US 301 over Boyds Corner Road (SR 896). Motorists should anticipate a single lane closure with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7 p.m. until 6 a.m. Wednesday, May 31 through Thursday, June 1 Continue […]


Read More

sr141

SR141/I-95 Ramp Interchange Project

Written on: May 24th, 2017 in SR141

SR141/I-95 Ramp Interchange Project May 19, 2017 The contractor, Mumford and Miller Inc., will be installing sheet piles to widen the I-95 acceleration lane from SR141. They will continue to form and pour a new deck for SR141 southbound and northbound. They will continue placing fill and pouring concrete curbs for the widening of SR141 […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the week of May 22.

Written on: May 19th, 2017 in US 301 Project UpdatesUS301

Monday, May 22 through Thursday, May 25 Continue repainting of temporary concrete barrier wall along US Route 13 south of the on ramp to State Route 1. Motorists should anticipate single left lane or right lane closures on northbound and southbound US 13 between Port Penn Road and the on ramp for State Route 1 […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week.

Written on: May 11th, 2017 in US 301 Project UpdatesUS301

Monday, May 15, 2017 through Thursday, May 18, 2017 Continue repainting of temporary concrete barrier wall along US 13 south of the on ramp to SR 1. Motorists should anticipate single left lane or right lane closures on northbound and southbound US 13 between Port Penn Road and the on ramp for SR 1 from […]


Read More


+