sr141

SR141/I-95 Ramp Interchange Project

Written on: January 20th, 2017 in SR141

SR141/I-95 Ramp Interchange Project January 13, 2017 The contractor, Mumford and Miller Inc., will be forming and pouring a new deck for SR141 southbound and installing storm drains on SR141 northbound. They will continue constructing the concrete structures for the new bridges and placing fill for the widening of SR141 southbound and northbound to I-95. […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: January 20th, 2017 in US 301 Project UpdatesUS301

Tuesday, January 24 through Thursday, January 26 Continue bridge construction activities along SR 1. Motorists should anticipate a left lane closure along northbound or southbound SR 1 between the Roth Bridge and Toll Plaza from 9 a.m. until 3 p.m. Monday, January 23 through Friday, January 27 Continue installing ITMS along the right shoulder of […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. ROUTE 301 Mainline Project during the next week.

Written on: January 13th, 2017 in US 301 Project UpdatesUS301

Tuesday, January 17, 2017 through Thursday, January 19, 2017 Continue bridge construction activities along State Route 1. Motorists should anticipate a left lane closure along northbound or southbound State Route 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m. Begin installing drainage pipe across existing U.S. Route 301 at the […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the this week.

Written on: January 9th, 2017 in US 301 Project UpdatesUS301

Tuesday, January 10, 2017 through Thursday, January 12, 2017 Continue bridge construction activities along State Route 1. Motorists should anticipate a left lane closure along northbound or southbound State Route 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m. Monday, January 9, 2017 through Friday, January 13, 2017 Continue installing […]


Read More

sr141

SR141/I-95 Ramp Interchange Project

Written on: January 5th, 2017 in SR141

SR141/I-95 Ramp Interchange Project January 3, 2017 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. The contractor will continue to place fill for the widening of SR141 southbound and northbound to I-95. Beam installation will take place on SR141 southbound and the placement of storm drains […]


Read More

sr141

SR141/I-95 Ramp Interchange Project

Written on: January 5th, 2017 in SR141

SR141/I-95 Ramp Interchange Project December 23, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. The contractor will continue to place fill for the widening of SR141 southbound and northbound to I-95. Beam installation will take place on SR141 southbound and the placement of storm drains […]


Read More

sr141

SR141/I-95 Ramp Interchange Project

Written on: January 5th, 2017 in SR141

SR141/I-95 Ramp Interchange Project December 16, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. The contractor will continue to place fill for the widening of SR141 southbound and northbound to I-95. This week, beam installation will begin on SR141 southbound and the placement of storm […]


Read More

us-301-project-updates

Tuesday, January 3 through Thursday, January 5

Written on: December 29th, 2016 in US 301 Project UpdatesUS301

Continue bridge construction activities along SR 1. Motorists should anticipate a left lane closure along northbound or southbound SR 1 between the Roth Bridge and Toll Plaza from 9 a.m. until 3 p.m. Tuesday, January 3 through Friday, January 6 Continue installing ITMS along the right shoulder of northbound U.S. Route 13. Motorists should anticipate […]


Read More

us-301-project-updates

Tuesday, December 27 through Thursday, December 29

Written on: December 23rd, 2016 in US 301 Project UpdatesUS301

Continue bridge construction activities along SR 1. Motorists should anticipate a left lane closure along southbound SR 1 between the Roth Bridge and Toll Plaza. Tuesday, December 27 through Friday, December 30 Continue installing ITMS along the right shoulder of northbound U.S. Route 13. Motorists should anticipate a right shoulder closure along northbound U.S. Route […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: December 16th, 2016 in US 301 Project UpdatesUS301

Sunday, December 18, 2016 through Friday, December 23, 2016 Strawberry Lane will be closed to traffic at U.S. Route 301 on December 19, 2016 and remain closed until approximately December 2017. Motorists wanting to access the east side of Strawberry Lane from U.S. Route 301 will follow Levels Road (SR 15) to Strawberry Lane. Motorists […]


Read More


+