DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

sr141

SR141/I-95 Ramp Interchange Project

Written on: October 25th, 2016 in SR141

SR141/I-95 Ramp Interchange Project October 21, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will continue to place fill for the widening of ramps from SR141 northbound and southbound to I-95 northbound and constructing the side slopes of southbound SR141. On […]


Read More

sr141

SR141/I-95 Ramp Interchange Project

Written on: October 25th, 2016 in SR141

SR141/I-95 Ramp Interchange Project October 14, 2016 The contractor, Mumford & Miller Inc., has completed driving piles on one side of both southbound and northbound SR141. They are constructing the concrete structures for the new bridges on SR141. This week, the contractor will continue to place fill for the widening of ramps from SR141 northbound […]


Read More

sr141

SR141/I-95 Ramp Interchange Project

Written on: October 25th, 2016 in SR141

SR141/I-95 Ramp Interchange Project October 7, 2016 The contractor, Mumford & Miller Inc., has completed driving piles on one side of both southbound and northbound SR141. They are constructing the concrete structures for the new bridges on SR141. This week, the contractor will continue to place fill for the widening of ramps from SR141 northbound […]


Read More

sr141

SR141/I-95 Ramp Interchange Project

Written on: October 25th, 2016 in SR141

SR141/I-95 Ramp Interchange Project September 30, 2016 The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. This week, the […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during this week.

Written on: October 24th, 2016 in US 301 Project UpdatesUS301

Monday, October 24, 2016 through Friday, October 28, 2016 – Dayshift Begin preliminary work for installation of the temporary concrete barrier wall on Summit Bridge Road, north of Armstrong Corner Road. Motorists should anticipate northbound and southbound lane closures on Summit Bridge Road, north of Armstrong Corner Road, with traffic alternating through the work zone […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during this week.

Written on: October 17th, 2016 in US 301 Project UpdatesUS301

Monday, October 17, 2016 through Friday, October 21, 2016 – Dayshift Begin installing roadway drainage pipes across existing northbound U.S. Route 301 between Strawberry Lane and the Maryland Line. Motorists should anticipate northbound or southbound lane closures along U.S. Route 301 between the Maryland Line and Strawberry lane with traffic alternating through the work zone […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: October 7th, 2016 in US 301 Project UpdatesUS301

Monday, October 10, 2016 through Friday, October 14, 2016 – Dayshift Begin installing drainage pipe across existing southbound U.S. Route 301 between Strawberry Lane and Middle Neck Road. Motorists should anticipate a single lane closure along southbound U.S. Route 301 between Merrimac Road Levels Road from 8:00 a.m. to 3:00 p.m. Continue relocating ITMS conduit […]


Read More

sr141

SR141/I95 Ramp Interchange Project

Written on: October 4th, 2016 in SR141

SR141/I-95 Ramp Interchange Project September 23, 2016 The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. This week, the […]


Read More

sr141

SR141/I95 Ramp Interchange Project

Written on: October 4th, 2016 in SR141

SR141/I-95 Ramp Interchange Project September 16, 2016 The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. This week, the […]


Read More

sr141

SR141/I95 Ramp Interchange Project

Written on: October 4th, 2016 in SR141

SR141/I-95 Ramp Interchange Project September 9, 2016 The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. This week, the […]


Read More


+