us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during this week.

Written on: October 24th, 2016 in US 301 Project UpdatesUS301

Monday, October 24, 2016 through Friday, October 28, 2016 – Dayshift Begin preliminary work for installation of the temporary concrete barrier wall on Summit Bridge Road, north of Armstrong Corner Road. Motorists should anticipate northbound and southbound lane closures on Summit Bridge Road, north of Armstrong Corner Road, with traffic alternating through the work zone […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during this week.

Written on: October 17th, 2016 in US 301 Project UpdatesUS301

Monday, October 17, 2016 through Friday, October 21, 2016 – Dayshift Begin installing roadway drainage pipes across existing northbound U.S. Route 301 between Strawberry Lane and the Maryland Line. Motorists should anticipate northbound or southbound lane closures along U.S. Route 301 between the Maryland Line and Strawberry lane with traffic alternating through the work zone […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: October 7th, 2016 in US 301 Project UpdatesUS301

Monday, October 10, 2016 through Friday, October 14, 2016 – Dayshift Begin installing drainage pipe across existing southbound U.S. Route 301 between Strawberry Lane and Middle Neck Road. Motorists should anticipate a single lane closure along southbound U.S. Route 301 between Merrimac Road Levels Road from 8:00 a.m. to 3:00 p.m. Continue relocating ITMS conduit […]


Read More

sr141

SR141/I95 Ramp Interchange Project

Written on: October 4th, 2016 in SR141

SR141/I-95 Ramp Interchange Project September 23, 2016 The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. This week, the […]


Read More

sr141

SR141/I95 Ramp Interchange Project

Written on: October 4th, 2016 in SR141

SR141/I-95 Ramp Interchange Project September 16, 2016 The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. This week, the […]


Read More

sr141

SR141/I95 Ramp Interchange Project

Written on: October 4th, 2016 in SR141

SR141/I-95 Ramp Interchange Project September 9, 2016 The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. This week, the […]


Read More

sr141

SR141/I95 Ramp Interchange Project

Written on: October 4th, 2016 in SR141

SR141/I-95 Ramp Interchange Project September 2, 2016 The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. LANE CLOSURES: Motorists […]


Read More

sr141

SR141/I95 Ramp Interchange Project

Written on: October 4th, 2016 in SR141

SR141/I-95 Ramp interchange Project August 19, 2016 The contractor, Mumford & Miller, Inc., continues the demolition of the SR141 northbound bridge. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. They are driving piles, pouring footers and have started the construction of […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during this week.

Written on: October 3rd, 2016 in US 301 Project UpdatesUS301

Monday, October 3, 2016 through Friday, October 7, 2016 – Dayshift Continue installing temporary concrete barrier wall along existing southbound U.S. Route 301 between Merrimac Road and Levels Road. Motorists should anticipate a single lane closure along southbound U.S. Route 301 between Merrimac Road Levels Road from 8:00 a.m. to 3:00 p.m. Continue relocating ITMS […]


Read More

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: September 9th, 2016 in US 301 Project UpdatesUS301

Friday, September 9, 2016 to Monday, September 12, 2016 Temporarily close Summit Bridge Road (U.S. Route 301) between Marl Pit Road and Old School House Road on Friday, September 9, 2016, at 8:00 p.m. through Monday, September 12, 2016, at 5:00 a.m. for the installation of a pre-cast box culvert. This closure will detour traffic […]


Read More


+