sr141

SR141/I95 Ramp Interchange Project

Written on: October 4th, 2016 in SR141

SR141/I-95 Ramp Interchange Project
September 23, 2016
The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. This week, the contractor continues to place fill for the widening of ramps from SR141 northbound and southbound to I-95 northbound.
LANE CLOSURES:

Motorists should expect traffic on SR141 southbound and northbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Monday thru Thursday.

Ramp Exit 5B (NB I-295 to NB SR141/Newport) remains closed until late June 2017. Northbound SR141/Newport should use Exit 5.


sr141

SR141/I95 Ramp Interchange Project

Written on: October 4th, 2016 in SR141

SR141/I-95 Ramp Interchange Project
September 16, 2016
The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. This week, the contractor will start placing fill for the widening of ramps from SR141 northbound and southbound to I-95 northbound.
LANE CLOSURES:

Motorists should expect traffic on SR141 southbound and northbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Monday thru Saturday.

Motorists should expect multiple lane closures on I-295 on Wednesday evening starting at 8PM.
Ramp Exit 5B (NB I-295 to NB SR141) remains closed until late June 2017. Northbound SR141 should use Exit 5.


sr141

SR141/I95 Ramp Interchange Project

Written on: October 4th, 2016 in SR141

SR141/I-95 Ramp Interchange Project
September 9, 2016
The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. This week, the contractor will start removing the steel girders from the old bridges. The work will create multiple closures during the evening hours. I included the traffic alert below.
LANE CLOSURES:

Tuesday evening, starting at 6PM, the ramps from SR141 northbound and southbound to I95 northbound will be closed. They will also start closing lanes on northbound 95. One lane will remain open through the night. Work will finish by 5AM on Wednesday morning.

Thursday evening, starting at 6PM, the ramp from SR141 southbound to I295 northbound will be closed until 5AM Friday morning.

Motorists should expect traffic on SR141 southbound and northbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Monday thru Saturday.
Ramp Exit 5B (NB I-295 to NB SR141) remains closed until late June 2017. Northbound SR141 should use Exit 5.


sr141

SR141/I95 Ramp Interchange Project

Written on: October 4th, 2016 in SR141

SR141/I-95 Ramp Interchange Project
September 2, 2016

The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening.

LANE CLOSURES:

Motorists should expect traffic on SR141 southbound and northbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Wednesday thru Saturday.

There will be intermittent lane closures on I-95/I-295 northbound during the hours 6PM to 5AM on Thursday evening into Friday morning.

Ramp Exit 5B (NB I-295 to NB SR141) remains closed until late June 2017. Northbound SR141 should use Exit 5.


sr141

SR141/I95 Ramp Interchange Project

Written on: October 4th, 2016 in SR141

SR141/I-95 Ramp interchange Project
August 19, 2016
The contractor, Mumford & Miller, Inc., continues the demolition of the SR141 northbound bridge. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. They are driving piles, pouring footers and have started the construction of the new bridge on SR141 southbound.
LANE CLOSURES:
Motorists should expect traffic on SR141 southbound and northbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Monday thru Friday.

There will be intermittent lane closures on I-95/I-295 northbound during the hours 6PM to 5AM, Monday thru Friday.

Ramp Exit 5B ( NB I-295 to NB SR141 ) remains closed until late June 2017. Northbound SR141 should use Exit 5.





+