Written on: June 27th, 2012 in Route 54
As of June 27, 2012, some additional drainage work is being done to correct some issues that were unforeseen in the original design. This work is expected to be complete July 13th.
The final electrical connections to the signal cabinet bases are being made to activate the new signals.
Work is continuing on the landscaping around the storm water management ponds. Work is ongoing throughout the project limits to clean up debris, remove the silt fence and topsoil and seed adjacent to the curb and sidewalk.
DelDOT thanks everyone for their patience during this construction project.