Written on: June 6th, 2012 in Route 54
As of June 7, 2012, all work on the north side related to sidewalks, entrances and handicap ramps is complete.
Work on the south side related to sidewalks, entrances and handicap ramps is presently being performed and is expected to be complete by next Friday.
All final pavement markings are complete.
Work is being performed to install the signal detection loops and pedestrian signal poles at each of the signalized intersections. This work is expected to be complete by Friday June 22. Upon completion the final electrical connections to the signal cabinet bases will be made to activate the new signals.
Work is continuing on the landscaping around the storm water management ponds.
Work is ongoing throughout the project limits to clean up debris, remove the silt fence and topsoil and seed adjacent to the curb and sidewalk.