DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

i-95

I-95/SR 1 Interchange Project – Update

Written on: June 16th, 2011 in I-95I95/SR1 Interchange

The contractor is continuing to aggressively pursue work on the project.  Tasks include excavation for the stormwater management ponds, drainage installation, placing fill material for Ramp G1, and the abutment and wingwalls on the west side of SR 1.  The contractor is driving piling for the abutment on the east side of SR 1.  Rehabilitation work on […]


Read More

irib

Indian River Inlet Bridge – Update

Written on: May 23rd, 2011 in Indian River Inlet Bridge

Concrete pours using the form traveler continue with nine of 24 total sections having been completed.   Other bridge building activities continue to progress as scheduled with the anticipated availability to traffic occurring by late 2011.  Currently, the Phase II traffic pattern is in effect.  Route 1 northbound and southbound will be in dual single-lane […]


Read More

elkton-road

Elkton Road Construction – Update

Written on: May 23rd, 2011 in Elkton Road

Phase 3 is scheduled to begin on May 31st.  This phase is the disincentive period where the contractor must reconstruct the northbound lanes of Elkton Road before the University of Delaware’s fall semester begins in August.  The City of Newark has added sanitary sewer work to the project that may delay our contractor’s work.  Work […]


Read More

i-95

I-95 Toll Plaza Project – Update

Written on: May 23rd, 2011 in I-95I-95 Delaware Toll Plaza

Final surface paving for northbound cash lanes (north and south of the plaza) continued throughout the week of May 16, weather permitting.  Installations of northbound overhead sign structure trusses between the Maryland state line and the toll plaza were rescheduled to begin Thursday night, 5/19/2011.  A left lane closure of southbound I-95 is needed to complete […]


Read More

i-95

I-95/SR 1 Interchange Project – Update

Written on: May 23rd, 2011 in I-95I95/SR1 Interchange

The contractor is continuing to aggressively pursue work on the project by working seven days a week.  Tasks include excavation for the stormwater management ponds, drainage installation, placing fill material for Ramp G1, and sheet pile installation for the Christiana Mall pond should begin by the end of the week.  The contractor has placed the concrete […]


Read More

irib

Indian River Inlet Bridge – Update

Written on: April 28th, 2011 in Indian River Inlet Bridge

Construction:    Currently, Skanska is working on the fourth pour of 12 pours on the northside of the bridge, and on pour three of 12 on the southside of the bridge.  New sets of stay cables will continue to be installed with each new 24’ section of bridge being constructed by the form traveler.   Proper stay […]


Read More

elkton-road

Elkton Road Construction – Update

Written on: April 21st, 2011 in Elkton Road

A value engineering proposal (VEP) has been proposed to and accepted by the Department to allow the contractor to enter into Phase III traffic pattern earlier than planned. The proposal allows the contractor an alternate method to install the new water main.  The VEP change will save DelDOT money  and will give the contractor a […]


Read More

i-95

I-95 Delaware Toll Plaza Project – Update

Written on: April 21st, 2011 in I-95I-95 Delaware Toll Plaza

Final surface paving of available southbound areas, south of the plaza is scheduled to begin Monday night, April 18, using  progressive single and double lane closures (all lanes).  Double lanes closures cannot begin until 11 PM.  Installations of northbound overhead sign structure trusses between the Maryland state line and the toll plaza are rescheduled to […]


Read More

i-95

I-95/SR 1 Interchange Project – Update

Written on: April 21st, 2011 in I-95I95/SR1 Interchange

Christiana Mall Bridge: Work started at the beginning of March to construct a new bridge spanning SR1 that will ultimately serve as a new entrance to Christiana Mall once completed.  This project is part of the larger mall interchange project that is currently out for bid.  The contractor is currently constructing storm water management facilities […]


Read More

irib

Indian River Inlet Bridge – Update

Written on: March 25th, 2011 in Indian River Inlet Bridge

George & Lynch was recently awarded the $11,625,940 project which will build the roadway approaches for the new Indian River Inlet Bridge and demolish the existing Indian River Inlet Bridge.  This work will include construction of the new roadway approaches to the new bridge and the demolition of the existing bridge. The first phase of […]


Read More


+