Written on: October 4th, 2016 in SR141
SR141/I-95 Ramp Interchange Project September 16, 2016 The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. This week, the […]
Written on: October 4th, 2016 in SR141
SR141/I-95 Ramp Interchange Project September 9, 2016 The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. This week, the […]
Written on: October 4th, 2016 in SR141
SR141/I-95 Ramp Interchange Project September 2, 2016 The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. LANE CLOSURES: Motorists […]
Written on: October 4th, 2016 in SR141
SR141/I-95 Ramp interchange Project August 19, 2016 The contractor, Mumford & Miller, Inc., continues the demolition of the SR141 northbound bridge. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. They are driving piles, pouring footers and have started the construction of […]
Written on: August 18th, 2016 in SR141
SR141/I-95 Ramp interchange Project August 12, 2016 The contractor, Mumford & Miller, Inc., continues the demolition of the SR141 northbound bridge. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. They are driving piles, pouring footers and have started the construction of […]
Written on: August 5th, 2016 in SR141
SR141/I-95 Ramp interchange Project August 5, 2016 The contractor, Mumford & Miller, Inc., continues the demolition of the SR141 northbound bridge. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. They are driving piles, pouring footers and have started the construction of […]
Written on: August 5th, 2016 in SR141
SR141/I-95 Ramp interchange Project July 29, 2016 The contractor, Mumford & Miller, Inc., continues the demolition of the SR141 northbound bridge. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. They are driving piles, pouring footers and have started the construction of […]
Written on: July 28th, 2016 in SR141
SR141/I-95 Ramp Interchange Project July 15, 2016 The contractor, Mumford & Miller, Inc., continues the clearing and grubbing of SR141 southbound/northbound and at ramps G and F in preparation for bridge widening work. They are driving piles, pouring footers and have started the construction of the new bridge on SR141 southbound. Evening work will continue […]
Written on: July 28th, 2016 in SR141
SR141/I-95 Ramp Interchange Project July 8, 2016 The contractor, Mumford & Miller Concrete, Inc., continues the clearing of SR141 southbound/northbound and at Ramps G and F in preparation for bridge widening work. The contractor continues to drive piles on the south side of SR141 southbound bridge. Barrier is being placed on SR141 northbound for the […]
Written on: July 6th, 2016 in SR141
SR141/I-95 Ramp Interchange Project July 1, 2016 The contractor, Mumford & Miller Concrete, Inc., will continue the clearing of SB 141 southbound along with the placement of fill as they prepare for the widening of the bridge over I-95 northbound. The contractor will be installing and pinning barriers on SR141 northbound in preparation for the […]