SR141/I-95 Ramp Interchange Project
September 16, 2016
The contractor, Mumford & Miller, Inc. have been driving piles and constructing concrete structures for the new bridges on SR141 southbound and northbound. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. This week, the contractor will start placing fill for the widening of ramps from SR141 northbound and southbound to I-95 northbound.
LANE CLOSURES:
Motorists should expect traffic on SR141 southbound and northbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Monday thru Saturday.
Motorists should expect multiple lane closures on I-295 on Wednesday evening starting at 8PM.
Ramp Exit 5B (NB I-295 to NB SR141) remains closed until late June 2017. Northbound SR141 should use Exit 5.