Written on: January 11th, 2019 in US 301 Project Updates US301
Monday, January 14, 2019, through Thursday, January 17, 2019 – Dayshift
Motorists should expect a single right lane closure on US 13 southbound from Lorewood Grove Road to Port Penn Road from 9:00 a.m. to 3:00 p.m. for work associated with the concrete barrier wall on the right hand shoulder.
Monday, January 14, 2019, through Friday, January 18, 2019 – Dayshift
Continue bridge construction activities on Boyds Corner Road (Route 896). Motorists should anticipate an eastbound or westbound lane closure on Boyds Corner Road (Route 896) west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 8:00 a.m. to 4:00 p.m.
Motorists should anticipate a single lane closure on Bunker Hill Road from the bridge over the new US 301 alignment to the roundabout at Chop Tank Road from 9:00 a.m. to 3:00 p.m. for curb and gutter construction.
Motorists should anticipate a single lane closure on Summit Bridge Road from Boyds Corner Road to Springmill Drive from 8:00 a.m. to 4:00 p.m. for excavation and topsoil placement.
Motorists should anticipate a single lane closure on both US 301 northbound and southbound from the Maryland State Line to the Delaware Weigh Station from 8:00 a.m. to 3:00 p.m. for stormwater management pond construction.
Monday, January 14, 2019, through Thursday, January 17, 2019 – Nightshift
Motorists should expect intermittent single right or left lane closures on SR 1 southbound from the Roth Bridge to Biddles Toll Plaza from 9:00 p.m. to 6:00 a.m. to remove overhang brackets on the new US 301 northbound bridge.
Motorists should expect intermittent single or double right or left lane closures on SR 1 northbound from Boyds Corner Road to the Roth Bridge from 10:00 p.m. to 5:00 a.m. to remove overhang brackets on the new US 301 northbound bridge.
Friday, January 18, 2019 – Dayshift
Motorists should expect a single right lane closure on US 13 Southbound from Lorewood Grove Road to Port Penn Road from 9:00 a.m. to 12:00 p.m. for work associated with the concrete barrier wall on the right hand shoulder.
Detours and Roadway Closures
The new US 301 alignment was opened to traffic and tolling on January 10, 2019 from the Maryland State Line to Route 1 in both directions including exits at Jamison Corner Road, the Connector Road to Summit Bridge Road, and Levels Road.
The Stadium/Bus lot and secondary driveway at St. Georges High School is closed to all traffic until further notice except during morning drop off and school dismissal times Monday through Friday. All other vehicles entering/exiting at any other time should use the main entrance to the high school.
Hyetts Corner Road is closed to traffic between the St. Georges High School and Windsor Commons Way. Motorists traveling westbound on Hyetts Corner Road should follow Jamison Corner Road through the roundabout and continue to Boyds Corner Road (SR 896) and turn left, follow Boyds Corner Road (Route 896) to US 13 and turn left, and back to Hyetts Corner Road. Motorists traveling eastbound on Hyetts Corner Road should turn right at US 13, follow US 13 to Boyds Corner Road (Route 896) and turn right, follow Boyds Corner Road to Jamison Corner Road and turn right, follow Jamison Corner road through the roundabout and back to Hyetts Corner Road.