Below is an outline of the anticipated construction schedule for the US 301 Mainline Project – January 5, 2019 through January 11, 2019

Written on: January 4th, 2019 in US 301 Project Updates US301

Saturday, January 05, 2019 through Wednesday January 09, 2019: Dayshift

Motorists should anticipate a single right or left lane closure on SR 1 Southbound between Biddle’s Toll Plaza and the Roth Bridge from 7:00 AM until 3:00 PM for completion of the US 301 SB Tie In.

Motorists should anticipate a single right lane closure on US 13 Southbound between St. George’s Bridge and Port Penn Rd from 7:00 AM until 3:00 PM for construction of roadside barrier.

Motorists should anticipate a lane shift on the newly opened ramp to SR 1 Northbound from 9:00AM to 4:00PM for striping and clean up activities.

Sunday, January 06, 2019 through Wednesday January 09, 2019: Nightshift

Motorists should anticipate a double right or left lane closure on SR 1 Southbound between Biddles Toll Plaza and the Roth Bridge from 10:00 PM until 5:00AM for removal of the overhangs on the new bridge over SR 1.

Monday, January 07, 2019, through Friday, January 11, 2019: Dayshift

Continue bridge construction activities on Boyds Corner Road. Motorists should anticipate an eastbound or westbound lane closure on Boyd Corner Road, west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 8:00 AM until 4:00 PM.

Motorists should expect single lane closures with flaggers directing traffic in both directions on Jamison Corner Road from Hyetts Corner Road south through the new US 301 interchange from 9:00 AM until 3:00 PM.

Motorists should anticipate a single lane closure on Bunker Hill Road from the bridge over the new US 301 alignment to the roundabout at Chop Tank Road from 9:00 AM until 3:00 PM for curb and gutter construction.

Motorists should anticipate a single lane closure on Armstrong Corner Road from Summit Bridge Road to the bridge going over Armstrong Corner Road from 9:00 AM until 3:00 PM for roadside grading.

Saturday, January 05, 2019, through Friday, January 11, 2019: Nightshift

Motorists should expect single lane closures with flaggers directing traffic in both directions on Jamison Corner Road from Hyetts Corner Road south through the new US 301 interchange from 7:00 PM until 6:00 AM.

Detours and Roadway Closures

The Stadium/Bus lot and secondary driveway at St. Georges High School is closed to all traffic until further notice except during morning drop off and school dismissal times Monday through Friday. All other vehicles entering/exiting at any other time should use the main entrance to the high school.

Hyetts Corner Road is closed to traffic between the St. Georges High School and Windsor Commons Way. Motorists traveling westbound on Hyetts Corner Road should follow Jamison Corner Road through the roundabout and continue to Boyds Corner Road and turn left, follow Boyds Corner Road to US 13 and turn left, and back to Hyetts Corner Road. Motorists traveling eastbound on Hyetts Corner Road should turn right at US 13, follow US 13 to Boyds Corner Road and turn right, follow Boyds Corner Road to Jamison Corner Road and turn right, follow Jamison Corner Road through the roundabout and back to Hyetts Corner Road.

 

 




+