
Facebook Twitter Flickr YouTube RSS Feed
Written on: March 9th, 2017 in US 301 Project Updates US301
Monday, March 13, 2017 through Thursday, March 16, 2017
Continue bridge construction activities along State Route 1. Motorists should anticipate single lane closures along northbound or southbound State Route 1 between the Roth Bridge and Toll Plaza from 9:00 a.m. to 3:00 p.m.
Monday, March 13, 2017 through Friday, March 17, 2017
Begin median reconstruction along existing U.S. Route 301 at Levels Road. Motorists should anticipate northbound and southbound left lane closures on existing U.S. Route 301 at Levels Road from 8:00 a.m. to 4:00 p.m.
Begin preliminary work for new traffic pattern and roadway widening. The northbound shoulder of Summit Bridge Road north and south of Armstrong Corner/Marl Pit Road will remain closed for roadway widening.
Continue dirt hauling and bridge construction activities on Boyd’s Corner Road. Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road west of Jamison Corner Road from 8:00 a.m. to 4:00 p.m.
Continue dirt hauling and other construction activities across Armstrong Corner Road. Motorists should anticipate a flagging operation by construction personnel on Armstrong Corner Road west of Summit Bridge Road from 7:00 a.m. to 5:00 p.m.
Continue dirt hauling and bridge construction activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7:00 a.m. to 5:00 p.m.
Hyetts Corner Road is closed to traffic between the St. Georges High School and Windsor Commons Way until December 2018. Motorists traveling westbound on Hyetts Corner Road should follow Jamison Corner Road through the roundabout and continue to Boyds Corner Road (State Route 896) and turn left, follow Boyds Corner Road (State Route 896) to U.S. Route 13 and turn left, and back to Hyetts Corner Road. Motorists traveling eastbound on Hyett’s Corner Road should turn right at U.S. Route 13, follow U.S. Route 13 to Boyds Corner Road (State Route 896) and turn right, follow Boyds Corner Road to Jamison Corner Road and turn right, follow Jamison Corner road through the roundabout and back to Hyetts Corner Road.
Middle Neck Roads is closed at U.S. Route 301. Motorists wishing to access Middle Neck Road from U.S. Route 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.
Strawberry Lane is closed to traffic at U.S. Route 301. Motorists wanting to access the east side of Strawberry Lane from U.S. Route 301 will follow Levels Road (State Route 15) to Strawberry Lane. Motorists wanting to access the west side of Strawberry Lane from U.S. Route 301 will follow Warwick Road (State Route 299) to Wilson Street/Strawberry Lane.