Written on: October 25th, 2016 in SR141
SR141/I-95 Ramp Interchange Project
October 14, 2016
The contractor, Mumford & Miller Inc., has completed driving piles on one side of both southbound and northbound SR141. They are constructing the concrete structures for the new bridges on SR141. This week, the contractor will continue to place fill for the widening of ramps from SR141 northbound and southbound to I-95 northbound and constructing the side slopes of southbound SR141.
LANE CLOSURES:
Motorists should expect traffic on SR141 southbound and northbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Monday thru Saturday.
Ramp Exit 5B (NB I-295 to NB SR141/Newport) remains closed until late June 2017. Northbound SR141/Newport should use Exit 5.