us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: June 17th, 2016 in US 301 Project UpdatesUS301

Monday, June 20, 2016 through Friday, June 24, 2016

Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00 a.m. to 5:00 p.m.

Begin roadway restoration work on Summit Bridge Road associated with the ESNG Utility relocation. Motorists should anticipate northbound or southbound lane closures on Summit Bridge Road, north and south of Armstrong Corner Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 8:00 p.m. to 5:00 a.m.

Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7:00 a.m. to 5:00 p.m.

Continue hauling activities across Middleneck Road. Motorists should anticipate a flagging operation by construction personnel for construction equipment crossing Middleneck Road from 7:00 a.m. to 5:00 p.m.


route-26

Route 26 Project Update

Written on: June 17th, 2016 in Route 26

Below is the anticipated work schedule and associated lane closures for work on the SR 26 Mainline Improvement Project along with suggested alternate routes for those of you who wish to bypass the SR 26 corridor.

Please be advised that there is a considerable amount of construction activity scheduled for next week.  Use of the alternate routes is strongly suggested.

Travel times to and from your destination may be quicker if you use one of the SR 26 Alternate Routes that were constructed prior to the start of the SR 26 Mainline Construction Project.

The recently reconstructed roadways include:

  • Burbage Road, from SR 17 to Windmill Drive
  • Windmill Drive to SR 26 to Central Avenue
  • Central Avenue, from Windmill Drive to Beaver Dam Road
  • Beaver Dam Road, from Central Avenue to Muddy Neck Road

 

Below is an outline of the anticipated construction schedule and associated lane closures for
work on the SR 26 Mainline Improvement Project during the next week.

Monday, June 20, 2016 through Thursday, June 23, 2016 – Day Shift

Continue placing concrete for new curb on Route 26 from Powell Farm Road to Irons Lane.
Motorists should anticipate eastbound or westbound shifts on Route 26 between Powell Farm
Road and Irons Lane with both lanes getting through the work zone utilizing a flagging operation
by construction personnel from 07:00AM to 5:00PM.

Continue wedge and leveling on Route 26 at Powell Farm Road, Omar Road, Roxana Road,
Central Avenue and West Avenue. Motorists should anticipate lane shifts along Route 26 at
these intersections with both travel lanes getting through the work zone utilizing a flagging
operation by Law Enforcement and construction personnel from 07:00AM to 5:00PM.

Continue paving driveway entrances along Route 26 between Railway Road and Powell Farm
Road. Motorists should anticipate lane shifts along Route 26 in this corridor with both travel
lanes getting through the work zone utilizing a flagging operation by construction personnel
from 07:00AM to 5:00PM.

Begin profile milling on Route 26 from the Assawoman Canal towards Powell Farm Road.
Motorists should anticipate eastbound or westbound lane shifts along the Route 26 corridor with
both lanes getting through the work zone utilizing a flagging operation by Law Enforcement
construction personnel from 07:00AM to 5:00PM.

 


route-26

Route 26 Scheduled Lane Closures

Written on: June 17th, 2016 in Route 26

Below is an outline of the anticipated construction schedule and associated lane closures for
work on the SR 26 Mainline Improvement Project during the next week.

Monday, June 13, 2016 through Thursday, June 16, 2016 – Day Shift

Continue placing concrete for new curb on Route 26 at Powell Farm Road. Motorists should
anticipate eastbound or westbound shifts on Route 26 at Powell Farm Road with both lanes
getting through the work zone utilizing a flagging operation by construction personnel from
07:00AM to 5:00PM.

Continue wedge and leveling on Route 26 between Roxana Road and Powell Farm Road.
Motorists should anticipate lane shifts along Route 26 in this corridor with both travel lanes
getting through the work zone utilizing a flagging operation by construction personnel from
07:00AM to 5:00PM.

Continue paving driveway entrances along Route 26 between Railway Road and Powell Farm
Road. Motorists should anticipate lane shifts along Route 26 in this corridor with both travel
lanes getting through the work zone utilizing a flagging operation by construction personnel
from 07:00AM to 5:00PM.

Thursday, June 16, 2016 – Night Shift
Continue wedge and leveling on Route 26 between Cedar Drive and Roxana Road. Motorists
should anticipate eastbound and westbound lane closures along Route 26 in this corridor with
traffic alternating through the work zone utilizing a flagging operation by Law Enforcement and
construction personnel from 9:00PM to 8:00AM.