Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: June 17th, 2016 in US 301 Project Updates US301

Monday, June 20, 2016 through Friday, June 24, 2016

Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00 a.m. to 5:00 p.m.

Begin roadway restoration work on Summit Bridge Road associated with the ESNG Utility relocation. Motorists should anticipate northbound or southbound lane closures on Summit Bridge Road, north and south of Armstrong Corner Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 8:00 p.m. to 5:00 a.m.

Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7:00 a.m. to 5:00 p.m.

Continue hauling activities across Middleneck Road. Motorists should anticipate a flagging operation by construction personnel for construction equipment crossing Middleneck Road from 7:00 a.m. to 5:00 p.m.