DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

i-95

Spring 2013 Project update

Written on: July 11th, 2013 in I-95 I95/SR1 Interchange

The northbound I-95 to northbound Route-7 ramp was opened in May 2013.

Structural steel beams for the bridges was delivered throughout the spring and is all in place. Construction continues on the rest of the bridges, decks, overpasses, roadway paving, and retaining walls.

 The project is about 80 % completed.

 The northbound Route-1 to northbound I-95 flyover ramps and the southbound I-95 to southbound Route-1 flyover ramps will be opened during the Fall.




+