DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

elkton-road

Elkton Road Construction – Updates

Written on: April 30th, 2012 in Elkton Road

Greggo & Ferrara will continue to grade for curb and sidewalk followed by placement of curb and sidewalk from Lincoln Dr to Veterans Dr with flagger controlled intermittent lane closures. Drainage pipe installation will continue on Apple Rd followed by Verizon underground duct relocation; this work is behind the PCC barrier placed for the southbound Apple Rd closure. Intersection reconstruction […]


Read More

route-54

Route 54 Project – Updates

Written on: April 27th, 2012 in Route 54

April 26, 2012 – DelDOT is making good progress on the Route 54 construction project, despite a few rain days during the week of April 18-April 26.  The contractor is continuing to work on installing the three lifts of asphalt pavement. On the north side of the project, the first lift has been completed, and […]


Read More

route-54

Route 54 Project – Updates

Written on: April 25th, 2012 in Route 54

April 13, 2012 –  DelDOT will perform weekend work on April 14 and April 15 . This work is to perform paving operations and will require daytime lane restrictions on April 14 and 15.  DelDOT will be working in earnest to complete as much work as possible before the Memorial Day holiday weekend. Also, DelDOT […]


Read More

elkton-road

Elkton Road Project Update

Written on: April 17th, 2012 in Elkton Road

Road excavation and GABC stone base placement will occur between Lincoln Dr and Veterans Dr with flagger controlled intermittent lane closures, as needed. Drainage pipe installation will continue between Veterans Dr and Apple Rd with intermittent lane closures. Fine grading of GABC stone base will occur between Casho Mill Rd and Lincoln Dr, no lane […]


Read More

route-54

Route 54 Project – Updates

Written on: April 4th, 2012 in Route 54

As of March 26 the Contractor has added an additional crew resulting in a total of 3 crews.  The crews are performing excavation of the existing roadway, minor drainage and placement/grading of stone base course for asphalt, curb and sidewalk.  In addition to the 3 crews for the general contractor there is 1 crew for […]


Read More

route-54

Route 54 Project – Updates

Written on: March 30th, 2012 in Route 54

Presently, the contractor has completed the excavation on the north side of the road and is completing the placement of the stone base.  The contractor has also begun the placement of the curb.  In the next few weeks, the contractor is hoping to begin placing the sidewalk and asphalt for the north side widening.  Presently, […]


Read More

i95sr1-interchange

I-95/SR 1 Interchange Project – Update

Written on: January 25th, 2012 in I95/SR1 Interchange

Christiana Mall Road Bridge: All three deck pours are complete.  This week the contractor will be preparing for the parapet wall construction.  The goal is to open the new bridge to traffic in mid to late March, but that date is very weather dependent. For more information, please visit the project website at i95.deldot.gov.


Read More

irib

Indian River Inlet Bridge – Update

Written on: December 30th, 2011 in Indian River Inlet Bridge

Finishing activities continue as the work progresses towards a January 2012 opening to traffic.  Some of the primary activities remaining to be performed prior to opening include: deck surface grinding and grooving, pavement striping, final stay tensioning adjustments, stay damper installation, pylon work platform removal, tower crane removal and final punchlist work.  Some additional work […]


Read More

irib

Indian River Inlet Bridge – Update

Written on: December 12th, 2011 in Indian River Inlet Bridge

Several finishing activities continue as the work progresses towards a January 2012 opening to traffic.  The concrete bridge barriers are complete and the new polyester polymer concrete (PPC) deck overlay work is on-going.  Bridge electrical and lighting work continues, but is not critical for the bridge opening.  Final tensioning adjustments and damper installation work also […]


Read More

elkton-road

Elkton Road Construction – Update

Written on: November 4th, 2011 in Elkton Road

The repair work to an approach slab on the south end of the project is scheduled to occur this weekend.  The Contractor will be performing a minor traffic switch this week at Casho Mill Road and plans to close the Elkton/Apple Road intersection this weekend for paving. Scheduled Completion Date: December 17, 2012


Read More


+