Written on: April 25th, 2012 in Route 54

April 13, 2012 –  DelDOT will perform weekend work on April 14 and April 15 . This work is to perform paving operations and will require daytime lane restrictions on April 14 and 15.  DelDOT will be working in earnest to complete as much work as possible before the Memorial Day holiday weekend. Also, DelDOT […]


Read More

route-54

Route 54 Project – Updates

Written on: April 4th, 2012 in Route 54

As of March 26 the Contractor has added an additional crew resulting in a total of 3 crews.  The crews are performing excavation of the existing roadway, minor drainage and placement/grading of stone base course for asphalt, curb and sidewalk.  In addition to the 3 crews for the general contractor there is 1 crew for […]


Read More

route-54

Route 54 Project – Updates

Written on: March 30th, 2012 in Route 54

Presently, the contractor has completed the excavation on the north side of the road and is completing the placement of the stone base.  The contractor has also begun the placement of the curb.  In the next few weeks, the contractor is hoping to begin placing the sidewalk and asphalt for the north side widening.  Presently, […]


Read More

route-54

Route 54 Project – Updates

Written on: November 4th, 2011 in Route 54

Phase 1 has been completed, which is all of the drainage, and are now in Phase 2.  Phase 2 consists of the widening on the south side of Route 54.  Excavation of the existing roadway has been completed, placement of the stone base, placement of the underdrain, and are continuing to place the electrical conduit.  Placement of […]


Read More

route-54

Route 54 Project – Updates

Written on: September 26th, 2011 in Route 54

Night work operations were extended through the month of September.  Day work is expected to resume on October 3.  The contractor  continues placement of the new drainage pipe.  A few remaining pipe runs cannot be completed due to conflicts with Verizon utilities.  Once the relocation is performed the drainage system will be completed.  The hot-mix wedging […]


Read More

route-54

Route 54 Project – Updates

Written on: August 29th, 2011 in Route 54

Night work operations for pipe installation continue until Labor Day. For more information, please visit the project website.


Read More

route-54

Route 54 Project – Updates

Written on: July 15th, 2011 in Route 54

See updates to the work schedule for Route 54 Improvement Project by visiting the project website.


Read More

route-54

Route 54 Project – Updates

Written on: June 16th, 2011 in Route 54

Beginning Friday June 17, there will be a change in the Route 54 work schedule since the project will be continuing through the summer. The Route 54 project is to widen the roadway between Route 20 and the Mallard Lakes development – it will include improved left turn lanes, bike lanes and sidewalks. Allowing work […]