Sunday, August 3 through Friday, August 8. Begin installation of sanitary sewer line along Route 26 between Irons Lane and Powell Farm Road. No lane closures are anticipated for this construction activity. Continue milling and paving of Central Avenue, north of Route 26. Motorists should anticipate eastbound or westbound lane closures on Route 26 between […]
Written on: July 24th, 2014 in Route 26
Sunday July 27, 2014 through Friday August 1, 2014 Begin milling and paving of Central Avenue, south of Route 26. Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation between 8:00 p.m. and 07:00 a.m. as well […]
Written on: July 24th, 2014 in Route 26
As a reminder, lane closure times have changed and construction activities involving a lane closure will begin on Sunday nights at 10:30 p.m. and conclude on Monday morning at 07:00 a.m. Additionally, Monday night through Friday morning, construction activities involving a lane closure will begin at 8:00 p.m. and conclude on at 07:00 a.m. the following morning. […]
Written on: July 18th, 2014 in Route 26
Sunday July 20, 2014 through Thursday July 24, 2014 Begin driving sheet piles at the southwest corner of Route 26/Cedar Drive for construction of new modular retaining wall. No lane closures are anticipated for this construction activity. Continue work on the installation of the new drainage system between Railway Road and Windmill Drive. Motorists should anticipate […]
Written on: July 18th, 2014 in Route 26
After careful review of the Transportation Management Plan that was developed as part of the SR 26 Mainline Project to assist in identifying the impacts of the construction of the SR 26 Mainline Project to the community and the traveling public, the Construction Management Team has decided to implement the following change to the lane […]
Written on: July 11th, 2014 in Route 26
One lane of Route 26 will be closed early Saturday morning for emergency roadwork. Motorists should anticipate the westbound lane of Route 26 to be closed between Railway Road and Clubhouse Road with traffic alternating through the work zone utilizing a flagging operation between 12 a.m. and 7 a.m. This emergency roadwork condition is the result of the […]
Written on: July 3rd, 2014 in Route 26
Monday, July 7, 2014, through Friday, July 11, 2014 Begin work on the installation of the new drainage system between Railway Road and Clubhouse Road. Motorists should anticipate the eastbound or westbound lane of Route 26 to be closed between Railway Road and Clubhouse Road with traffic alternating through the work zone utilizing a flagging […]
Written on: July 1st, 2014 in Route 26
On Wednesday, July 2, 2014, one lane of Powell Farm Road south of Route 26 will be closed for construction activities. George & Lynch, Inc. of Dover, Delaware will be performing grading activities adjacent to the edge of the travel lane along Powell Farm Road, south of Route 26. Motorists should anticipate the northbound or […]
Written on: June 30th, 2014 in Route 26
Monday June 30, 2014 through Thursday July 3, 2014 Begin minor grading activities at Omar Road and Route 26. No lane closures are anticipated for this work. Begin excavation of Storm Water Management Pond #333 located at Windmill Drive and Route 26. No lane closures are anticipated for this work. Continue reconstruction of the Central Avenue/Route 26 intersection […]
Written on: June 24th, 2014 in Route 26
On Thursday, June 26, 2014 and Friday, June 27, 2014, one lane of Powell Farm Road south of Route 26 will be closed for construction activities. George & Lynch, Inc. of Dover, Delaware will be performing roadway widening activities along Powell Farm Road, south of Route 26. Motorists should anticipate the northbound or southbound lane of […]