Anticipated construction schedule and associated lane closures for work on the Route 26 Widening Project during the next two weeks.

Written on: July 3rd, 2014 in Route 26

Monday, July 7, 2014, through Friday, July 11, 2014

 Begin work on the installation of the new drainage system between Railway Road and Clubhouse Road. Motorists should anticipate the eastbound or westbound lane of Route 26 to be closed between Railway Road and Clubhouse Road with traffic alternating through the work zone utilizing a flagging operation between 7:00 p.m. and 06:00 a.m.

 Continue reconstruction of the Old Mill Road/Route 26 intersection. Motorists should anticipate   lane closures at Old Mill Road and Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 7:00 p.m. and 06:00 a.m.

 Continue reconstruction of the Central Avenue/Route 26 intersection and water main relocation work between Woodland Avenue and Central Avenue. Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation between 7:00 p.m. and 06:00 a.m. as well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 7:00 p.m. and 06:00 a.m.

Continue work on the installation of the new drainage system between Cedar Drive and Grants Avenue. Motorists should anticipate the eastbound or westbound lane of Route 26 to be closed between Cedar Drive and Grants Avenue with traffic alternating utilizing a flagging operation between 07:00 p.m. and 6:00 a.m.

Continue excavation of Storm Water Management Pond #332 located east of Route 17 (Roxana Road) during the day. No lane closures are anticipated for this work.

Continue excavation of Storm Water Management Pond #333 located at Windmill Drive and Route 26. No lane closures are anticipated for this week.

Monday July 14, 2014 through Friday July 18, 2014

Continue the installation of the new drainage system between Railway Road and Clubhouse Road. Motorists should anticipate the eastbound or westbound lane of Route 26 to be closed between Railway Road and Clubhouse Road with traffic alternating through the work zone utilizing a flagging operation between 7:00 p.m. and 06:00 a.m.

Continue work on the installation of the new drainage system between Cedar Drive and Grants Avenue. Motorists should anticipate the eastbound or westbound lane of Route 26 to be closed between Cedar Drive and Grants Avenue with traffic alternating utilizing a flagging operation between 07:00 p.m. and 6:00 a.m.

Continue reconstruction of the Old Mill Road/Route 26 intersection. Motorists should anticipate   lane closures at Old Mill Road and Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 7:00 p.m. and 06:00 a.m.

Continue reconstruction of the Central Avenue/Route 26 intersection and the installation of the new drainage system between Woodland Avenue and Central Avenue. Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation between 7:00 p.m. and 06:00 a.m. as well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 7:00 p.m. and 06:00 a.m.

Continue excavation of Storm Water Management Pond #332 located east of Route 17 (Roxana Road) during the day. No lane closures are anticipated for this work.

Continue excavation of Storm Water Management Pond #333 located east of Route 17 (Roxana Road) during the day. No lane closures are anticipated for this work.

 




+