I-95/SR 1 Interchange Project – Update

Written on: July 15th, 2011 in I-95I95/SR1 Interchange

The Department of Transportation (DelDOT) announced that Cherry Hill Construction Company from Jessup, Maryland has officially been awarded the contract to reconstruct and reconfigure the Route 1 & I-95 Interchange. The project is expected to be completed in a little over 2-years, which is a full year earlier than anticipated. Cherry Hill Construction submitted a […]


Read More

i-95

I-95/SR 1 Interchange Project – Update

Written on: June 16th, 2011 in I-95I95/SR1 Interchange

The contractor is continuing to aggressively pursue work on the project.  Tasks include excavation for the stormwater management ponds, drainage installation, placing fill material for Ramp G1, and the abutment and wingwalls on the west side of SR 1.  The contractor is driving piling for the abutment on the east side of SR 1.  Rehabilitation work on […]


Read More

i-95

I-95/SR 1 Interchange Project – Update

Written on: May 23rd, 2011 in I-95I95/SR1 Interchange

The contractor is continuing to aggressively pursue work on the project by working seven days a week.  Tasks include excavation for the stormwater management ponds, drainage installation, placing fill material for Ramp G1, and sheet pile installation for the Christiana Mall pond should begin by the end of the week.  The contractor has placed the concrete […]


Read More

i-95

I-95/SR 1 Interchange Project – Update

Written on: April 21st, 2011 in I-95I95/SR1 Interchange

Christiana Mall Bridge: Work started at the beginning of March to construct a new bridge spanning SR1 that will ultimately serve as a new entrance to Christiana Mall once completed.  This project is part of the larger mall interchange project that is currently out for bid.  The contractor is currently constructing storm water management facilities […]


Read More

i-95

I-95/SR 1 Interchange Project – Update

Written on: March 22nd, 2011 in I-95I95/SR1 Interchange

Christiana Mall Bridge Work started at the beginning of March to construct a new bridge spanning SR1 that will ultimately serve as a new entrance to Christiana Mall once completed.  This project is part of the larger mall interchange project that is currently out for bid.  The contractor is currently clearing the work site and […]


Read More

i-95

SR1/I95 Interchange Project – Update

Written on: December 8th, 2010 in I-95I95/SR1 Interchange

SR1/I95 Interchange – Contract # T200809003.01 – The advertisement for bid proposals for this contract began on December 6, 2010.  A mandatory pre-bid meeting will be held on January 12, 2011, at 10:30 am at the DelDOT Administration Building.  Bids are scheduled to be opened on March 3, 2011, at 2 pm. If you would like more […]


Read More

i-95

SR1/I95 Interchange Project

Written on: November 8th, 2010 in I-95I95/SR1 Interchange

SR1/I95 Interchange – Contract # T200809003 – This contract has an anticipated advertisement date of late November 2010. If you would like more information about the project, please visit the Advertising/Bid Calendar or the project website.


Read More

i-95

SR1/I95 Interchange, Christiana Mall Road Bridge

Written on: November 5th, 2010 in I-95I95/SR1 Interchange

SR1/I95 Interchange, Christiana Mall Road Bridge – Contract # T201009004 – This project has been advertised. If you would like more information about the project, please visit the Advertising/Bid Calendar or the project website.


Read More


+