SR141/I-95 Ramp Interchange Project
November 18, 2016
The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will place fill for the widening of SR141 southbound and northbound to I-95.
LANE CLOSURES:
Motorists should expect traffic on SR141 northbound and southbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Monday and Tuesday of this week. There were be no lane closures during the holiday weekend. Closures will resume on Tuesday, November 29.
Ramp Exit 5B (NB I-295 to NB SR141/Newport) remains closed until late June 2017. Northbound SR141/Newport should use Exit 5.