Below is an outline of the anticipated construction schedule and associated lane closures for
work on the SR 26 Mainline Improvement Project during the next week.
Sunday, July 31, 2016 – Night Shift
Continue final paving activities on Route 26 between Old Mill Road and Powell Farm Road.
Motorists should anticipate eastbound and westbound lane closures on Route 26 between Old
Mill Road and Powell Farm Road with traffic alternating through the work zone utilizing a
flagging operation by construction personnel and Law Enforcement from 10:30PM to 7:00AM.
Monday, August 1, 2016 through Thursday, August 4, 2016 – Nightshift
Continue final paving activities on Route 26 between Old Mill Road and Powell Farm Road.
Motorists should anticipate eastbound and westbound lane closures on Route 26 between Old
Mill Road and Powell Farm Road with traffic alternating through the work zone utilizing a
flagging operation by construction personnel and Law Enforcement from 9:00PM to 8:00AM.
Monday, August 1, 2016 through Thursday, August 4, 2016 – Dayshift
Continue placing concrete for new curb and sidewalk on Central Avenue between Route 26 and
Woodland Avenue. Motorists should anticipate northbound lane closures on Central Avenue
between Woodland Avenue and Route 26 with traffic alternating through the work zone utilizing
a flagging operation by construction personnel from 7:00AM to 5:00PM.
Begin paving driveways and entrances along Route 26 between Old Mill Road and Powell Farm
Road. Motorists should anticipate eastbound or westbound lane shifts on Route 26 at between
Old Mill Road and Powell Farm Road with both lanes getting through the work zone utilizing a
flagging operation by construction personnel from 07:00AM to 5:00PM.