DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week.

Written on: June 15th, 2018 in US 301 Project Updates US301

Monday, June 18, 2018 through Thursday June 21, 2018 – Dayshift

Continue bridge construction activities along SR 1. Motorists should anticipate a single left or right lane closure along northbound and southbound SR 1 between the Biddles Toll Plaza and the Roth Bridge from 9:00 a.m. to 3:00 p.m.

Continue roadway widening activities along southbound US 13. Motorists should anticipate a single right lane closure along southbound US 13 between the Free Ramp to SR 1 and Port Penn Road from 9:00 a.m. to 2:00 p.m.

Continue roadway widening activities along northbound US 13. Motorists should anticipate a single right lane closure along northbound US 13 prior to the Free Ramp to SR 1 from 9:00 a.m. to 2:00 p.m.

Continue bridge construction activities along Bunker Hill Road. Motorists should anticipate an eastbound or westbound lane closure on Bunker Hill Road, west of Choptank Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00 a.m. to 5:00 p.m.

Continue bridge construction activities on Boyd’s Corner Road (SR 896). Motorists should anticipate an eastbound or westbound lane closure on Boyd’s Corner Road (SR 896) west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.

Monday, June 18, 2018 through Tuesday, June 19, 2018 – Nightshift

Milling and paving along southbound US 13. Motorists should anticipate a single right or left lane closure along southbound US 13 between the “free ramp” to northbound SR 1 Hyetts Corner Road from 7:00 p.m. to 8:00 a.m.

Wednesday, June 20, 2018 through Thursday, June 21, 2018 – Nightshift

Milling and paving along northbound US 13. Motorists should anticipate a single right or left lane closure along northbound US 13 between Hyetts Corner Road and the “free ramp” to northbound SR 1 from 5:00 p.m. to 6:00 a.m.

Detours and Roadway Closures

Port Penn Road at US 13 is restricted to a right turn into and right turn out of Port Penn Road. Traffic accessing southbound US 13 from Port Penn Road will follow Port Penn Road to Pole Bridge Road and back to US 13. Traffic accessing Port Penn Road from southbound US 13 will follow US 13 to Pole Bridge Road and back to Port Penn Road. Traffic accessing the Biddles Toll Plaza from northbound US 13 will follow US 13 to the traffic signal at the free ramp to northbound SR 1 and make a U-Turn back to the Biddles Toll Plaza. This closure will remain in effect through July 2018 after the intersection is reconstructed and the new traffic signal becomes operational.

Hyetts Corner Road is closed to traffic between the St. Georges High School and Windsor Commons Way until December 2018. Motorists traveling westbound on Hyetts Corner Road should follow Jamison Corner Road through the roundabout and continue to Boyds Corner Road (SR 896) and turn left, follow Boyds Corner Road (SR 896) to US 13 and turn left, and back to Hyetts Corner Road. Motorists traveling eastbound on Hyetts Corner Road should turn right at US 13, follow US 13 to Boyd’s Corner Road (SR 896) and turn right, follow Boyd’s Corner Road to Jamison Corner Road and turn right, follow Jamison Corner road through the roundabout and back to Hyetts Corner Road.




+