Written on: December 29th, 2016 in US 301 Project Updates, US301
Continue bridge construction activities along SR 1. Motorists should anticipate a left lane closure along northbound or southbound SR 1 between the Roth Bridge and Toll Plaza from 9 a.m. until 3 p.m.
Tuesday, January 3 through Friday, January 6
Continue installing ITMS along the right shoulder of northbound U.S. Route 13. Motorists should anticipate a right shoulder closure along northbound U.S. Route 13 between Old Hyetts Road and Port Penn Road from 9 a.m. until 3 p.m.
Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7 a.m. until 4 p.m.
Continue dirt hauling activities on Boyds Corner Road. Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road west of Jamison Corner Road from 8 a.m. until 4 p.m.
Continue dirt hauling activities across Armstrong Corner Road. Motorists should anticipate a flagging operation by construction personnel on Armstrong Corner Road west of Summit Bridge Road from 7 a.m. until 5 p.m.
Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7 a.m. until 5 p.m.
Middle Neck Road is closed at U.S. Route 301. Motorists wishing to access Middle Neck Road from U.S. Route 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.
Strawberry Lane is closed to traffic at U.S. Route 301 and remain closed until approximately December 2017. Motorists wanting to access the east side of Strawberry Lane from U.S. Route 301 will follow Levels Road (SR 15) to Strawberry Lane. Motorists wanting to access the west side of Strawberry Lane from U.S. Route 301 will follow Warwick Road (SR 299) to Wilson Street/Strawberry Lane.
Written on: December 23rd, 2016 in US 301 Project Updates, US301
Continue bridge construction activities along SR 1. Motorists should anticipate a left lane closure along southbound SR 1 between the Roth Bridge and Toll Plaza.
Tuesday, December 27 through Friday, December 30
Continue installing ITMS along the right shoulder of northbound U.S. Route 13. Motorists should anticipate a right shoulder closure along northbound U.S. Route 13 between Old Hyetts Road and Port Penn Road from 9 a.m. until 3 p.m.
Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7 a.m. until 5 p.m.
Continue dirt hauling activities on Boyds Corner Road. Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road west of Jamison Corner Road from 8 a.m. until 4 p.m.
Continue dirt hauling activities across Armstrong Corner Road. Motorists should anticipate a flagging operation by construction personnel on Armstrong Corner Road west of Summit Bridge Road from 7 a.m. until 5 p.m.
Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7 a.m. until 5 p.m.
Middle Neck Road is closed at U.S. Route 301 and will remain closed until the end of December of 2016. Motorists wishing to access Middle Neck Road from U.S. Route 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.
Strawberry Lane is closed to traffic at U.S. Route 301 and remain closed until approximately December 2017. Motorists wanting to access the east side of Strawberry Lane from U.S. Route 301 will follow Levels Road (SR 15) to Strawberry Lane. Motorists wanting to access the west side of Strawberry Lane from U.S. Route 301 will follow Warwick Road (SR 299) to Wilson Street/Strawberry Lane.
Written on: December 16th, 2016 in US 301 Project Updates, US301
Sunday, December 18, 2016 through Friday, December 23, 2016
Strawberry Lane will be closed to traffic at U.S. Route 301 on December 19, 2016 and remain closed until approximately December 2017. Motorists wanting to access the east side of Strawberry Lane from U.S. Route 301 will follow Levels Road (SR 15) to Strawberry Lane. Motorists wanting to access the west side of Strawberry Lane from U.S. Route 301 will follow Warwick Road (SR 299) to Wilson Street/Strawberry Lane.
Begin installing temporary concrete barrier on existing U.S. Route 301 from the Maryland Line to Strawberry Lane. Motorists should anticipate a northbound or southbound lane closure on existing U.S. Route 301 between the Maryland Line and Strawberry Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 8:00 a.m. to 3:00 p.m.
Continue installing ITMS along the right shoulder of southbound State Route 1. Motorists should anticipate a right shoulder closure along southbound state Route 1 between the Roth Bridge and Toll Plaza.
Continue installing ITMS along the right shoulder of northbound U.S. Route 13. Motorists should anticipate a right shoulder closure along northbound U.S. Route 13 between Old Hyetts Road and Port Penn Road from 9:00 a.m. to 3:00 p.m.
Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00 a.m. to 5:00 p.m.
Continue dirt hauling activities on Boyds Corner Road. Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road west of Jamison Corner Road from 8:00 a.m. to 4:00 p.m.
Continue dirt hauling activities across Armstrong Corner Road. Motorists should anticipate a flagging operation by construction personnel on Armstrong Corner Road west of Summit Bridge Road from 7:00 a.m. to 5:00 p.m.
Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7:00 a.m. to 5:00 p.m.
Middle Neck Road is closed at U.S. Route 301 and will remain closed until the end of December of 2016. Motorists wishing to access Middle Neck Road from U.S. Route 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.
Written on: December 13th, 2016 in SR141
SR141/I-95 Ramp Interchange Project
December 2, 2016
The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will place fill for the widening of SR141 southbound and northbound to I-95.
LANE CLOSURES:
Motorists should expect traffic on SR141 northbound and southbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Monday thru Friday.
Ramp Exit 5B (NB I-295 to NB SR141/Newport) remains closed until late June 2017. Northbound SR141/Newport should use Exit 5.
Looking ahead, motorists should expect multiple lane and ramp closures on I-95 and I-295 during the week of December 12th.
Written on: December 13th, 2016 in SR141
SR141/I-95 Ramp Interchange Project
November 18, 2016
The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will place fill for the widening of SR141 southbound and northbound to I-95.
LANE CLOSURES:
Motorists should expect traffic on SR141 northbound and southbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Monday and Tuesday of this week. There were be no lane closures during the holiday weekend. Closures will resume on Tuesday, November 29.
Ramp Exit 5B (NB I-295 to NB SR141/Newport) remains closed until late June 2017. Northbound SR141/Newport should use Exit 5.
Written on: December 9th, 2016 in US 301 Project Updates, US301
Sunday, December 11, 2016 through Saturday, December 17, 2016
Begin placing concrete for new bridge pier along southbound State Route 1. Motorists should anticipate single lane closures on southbound State Route 1 between the Roth Bridge and the Toll Plaza from 9 a.m. to 3:00 p.m.
Continue removing existing pipe culvert along Port Penn Road, east of U.S. Route 13. Motorists should anticipate lane closures on Port Penn Road east of U.S. Route 13 with traffic alternating through the work zone utilizing a flagging activity by construction personnel from 9:00 a.m. to 3:00 p.m.
Continue pile driving activities in the median of State Route 1, north of the toll plaza. No lane closures are anticipated for this activity.
Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00 a.m. to 5:00 p.m.
Continue dirt hauling activities on Boyds Corner Road. Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road west of Jamison Corner Road from 8:00 a.m. to 4:00 p.m.
Continue dirt hauling activities across Armstrong Corner Road. Motorists should anticipate a flagging operation by construction personnel on Armstrong Corner Road west of Summit Bridge Road from 7:00 a.m. to 5:00 p.m.
Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7:00 a.m. to 5:00 p.m.
Middle Neck Roads is closed at U.S. Route 301 and will remain closed until the end of December of 2016. Motorists wishing to access Middle Neck Road from U.S. Route 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.