Monday, August 29, 2016 through Thursday, September 1, 2016 – Dayshift
Begin preparations for box culvert construction on Summit Bridge Road. Motorists should anticipate a right shoulder closure on northbound Summit Bridge Road, north of Marl Pit Road from 7:00 a.m. – 5:00 p.m.
Begin installing temporary concrete barrier wall along existing southbound U.S. Route 301 between Merrimac Road and Levels Road. Motorists should anticipate a single lane closure along southbound U.S. Route 301 between Merrimac Road Levels Road from 8:00a.m. to 3:00 p.m.
Monday, August 29, 2016 through Saturday, September 3, 2016 – Dayshift
Access to the Biddles Toll Plaza E-ZPass Customer Service Center from northbound State Route 1 is closed. Motorists wishing to access the Biddles Plaza E-ZPass Customer Service Center must use the entrance from U.S. Route 13.
Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00 a.m. to 5:00 p.m.
Continue dirt hauling activities on Boyds Corner Road. Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road west of Jamison Corner Road from 8:00 a.m. to 4:00 p.m.
Continue dirt hauling activities across Armstrong Corner Road. Motorists should anticipate a flagging operation by construction personnel on Armstrong Corner Road west of Summit Bridge Road from 7:00 a.m. to 5:00 p.m.
Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7:00 a.m. to 5:00 p.m.
Middle Neck Roads is closed at U.S. Route 301 and will remain closed until the end of December of 2016. Motorists wishing to access Middle Neck Road from U.S. Route 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.
Monday, August 29, 2016 through Thursday, September 1, 2016 – Nightshift
Begin line striping activities along northbound and southbound State Route 1, south of the Roth Bridge. Motorists should anticipate northbound southbound lane closures along State Route 1 between the Roth Bridge and the Biddles Toll Plaza from 7:00 p.m. to 6:00 a.m.
Begin the installation of temporary concrete barrier wall along northbound U.S. Route 13. Motorists should anticipate single lane closures along northbound U.S. Route 13 north of the Biddles Toll Plaza (Port Penn Road) from 9:00 a.m. to 3:00 p.m.