DelDOT logo
DelDOT Blog


Delaware Department of Transportation


Facebook  Twitter  Flickr  YouTube  RSS Feed

us-301-project-updates

Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during this week.

Written on: August 22nd, 2016 in US 301 Project Updates US301

Monday, August 22, 2016 through Saturday, August 27, 2016 – Dayshift

Access to the Biddles Toll Plaza E-ZPass Customer Service Center from northbound State Route 1 is closed. Motorists wishing to access the Biddles Plaza E-ZPass Customer Service Center must use the entrance from U.S. Route 13.

Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00 a.m. to 5:00 p.m.

Continue dirt hauling activities on Boyds Corner Road. Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road west of Jamison Corner Road from 8:00 a.m. to 4:00 p.m.

Continue dirt hauling activities across Armstrong Corner Road. Motorists should anticipate a flagging operation by construction personnel on Armstrong Corner Road west of Summit Bridge Road from 7:00 a.m. to 5:00 p.m.

Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7:00 a.m. to 5:00 p.m.

Middle Neck Roads is closed at U.S. Route 301 and will remain closed until the end of December of 2016. Motorists wishing to access Middle Neck Road from U.S. Route 301 should follow the posted detour of Bunker Hill Road to Old Telegraph Road and back to Middle Neck Road.

Begin installing Temporary Concrete Barrier wall along existing southbound US 301 between Merrimac Road and Levels Road. Motorists should anticipate a single lane closure along southbound U.S. Route 301 between Merrimac Road Levels Road from 8:00 a.m. to 3:00 p.m.

Tuesday, August 23, 2016 through Thursday, August 25, 2016 – Nightshift

Install Temporary Concrete Barrier wall, demo rumble strips and repave shoulder along the left and right shoulder of State Route 1, south of the Roth Bridge. Motorists should anticipate northbound and south bound single lane closures along State Route 1 between the Roth Bridge and the Biddles Toll Plaza from 7:00 p.m. to 6:00 a.m.

Begin the installation of temporary concrete barrier wall along southbound US 13. Motorists should anticipate single lane closures along southbound U.S. Route 13 north of the Biddles Toll Plaza (Port Penn Road).




+