Sr141/I-95 Ramp Interchange Project

Written on: August 5th, 2016 in SR141

SR141/I-95 Ramp interchange Project
August 5, 2016

The contractor, Mumford & Miller, Inc., continues the demolition of the SR141 northbound bridge. They continue the clearing and grubbing of SR141 southbound, northbound and at ramps G and F in preparation for the bridge widening. They are driving piles, pouring footers and have started the construction of the new bridge on SR141 southbound.

LANE CLOSURES:

Motorists should expect traffic on SR141 southbound and northbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Monday thru Friday.

On Tuesday morning, August 9th, there will be a rolling roadblock between the hours of
1AM and 5AM.

Ramp Exit 5B ( NB I-295 to NB SR141 ) remains closed until late June 2017. Northbound SR141 should use Exit 5.




+