Below is an outline of the anticipated construction schedule and associated lane closures for work on the U.S. Route 301 Mainline Project during the next week.

Written on: July 29th, 2016 in US 301 Project Updates US301

Monday, August 1, 2016 through Saturday, August 6, 2016

Access to the Biddles Toll Plaza Customer Service Building from northbound State Route 1 will be closed on Monday, August 1, 2016 at 6:00 p.m. Motorists wishing to access the Biddles Plaza Customer Service Building must use the entrance from U.S. Route 13.

Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00 a.m. to 5:00 p.m.

Continue dirt hauling activities on Boyds Corner Road. Motorists should anticipate a flagging operation by construction personnel on Boyds Corner Road west of Jamison Corner Road from 8:00 a.m. to 4:00 p.m.

Begin dirt hauling activities across Armstrong Corner Road. Motorists should anticipate a flagging operation by construction personnel on Armstrong Corner Road west of Summit Bridge Road from 7:00 a.m. to 5:00 p.m.