SR141/I-95 Ramp Interchange Project Update
April 29, 2016
The contractor, Mumford & Miller, Inc., will complete the drainage improvements between I-95 and I-295 to allow the construction of a temporary cross-over for traffic control purposes. Work continues to clear 141 southbound in preparation for bridge widening work over I-95 northbound. Delmarva has begun the temporary relocation of a gas main off of 141 northbound in preparation for widening of that bridge. Work will begin on Airport Road between NB141 and SB141 to convert to one way traffic eastbound.
LANE CLOSURES:
Motorists should expect traffic on SR141 northbound and southbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Monday thru Friday.
There will be intermittent lane closures on northbound I-95/I-295 from 6PM to 5AM.
NEW CLOSURE:
Airport Road between NB141 to SB141 will be closed to NB141 traffic on or about May 3rd.




+