Facebook Twitter Flickr YouTube RSS Feed
Written on: July 1st, 2016 in US 301 Project Updates US301
Tuesday, July 5, 2016 through Saturday, July 9, 2016
Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 7:00 a.m. to 5:00 p.m.
Continue dirt hauling activities across Bunker Hill Road. Motorists should anticipate a flagging operation by construction personnel on Bunker Hill Road near Appoquinimink High School from 7:00 a.m. to 5:00 p.m.
Continue hauling activities across Middleneck Road. Motorists should anticipate a flagging operation by construction personnel for construction equipment crossing Middleneck Road from 7:00 a.m. to 5:00 p.m.