
Facebook Twitter Flickr YouTube RSS Feed
Written on: April 22nd, 2016 in US 301 Project Updates
Monday, April 25, 2016 through Saturday, April 30, 2016
Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.
Continue work on relocating the ESNG Utility. Motorists should anticipate a lane shift on Summit Bridge Road, north and south of Armstrong Corner Road with both travel lanes getting through the work zone.
Begin excavating for new ditches along Bunker Hill Road in the area of Appoquinimink High school. No lane closures are needed for this construction activity.
Begin dirt hauling activities across Bunker Hill Road. Motorists should anticipate lane closures on Bunker Hill Road near Appoquinimink High School with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.