Written on: September 8th, 2014 in Route 26
Monday, September 8, 2014 through Friday September 12, 2014
Continue milling and paving of Route 26 between Cedar Drive and Old Mill Road. Motorists
should anticipate eastbound or westbound lane closures on Route 26 between Cedar Drive and Old
Mill Road with traffic alternating through the work zone utilizing a flagging operation and with
traffic alternating through the intersection of Route 26 and Old Mill Road utilizing a flagging
operation by law enforcement and construction personnel between 7:00 p.m. and 06:00 a.m.
Begin milling and paving on Cedar Drive south of Route 26. Motorists should anticipate lane
closures on Cedar Drive at Route 26 with traffic alternating through the intersection utilizing a
flagging operation by construction personnel between 7:00 p.m. and 06:00 a.m.
Continue grading for curb and gutter between Old Mill Road and Cedar Drive. Motorists should
anticipate eastbound or westbound lane closures on Route 26 between Old Mill Road and Cedar
Drive with traffic alternating through the work zone utilizing a flagging operation as well as lane
closures Old Mill Road at Route 26 with traffic alternating through the intersection utilizing a
flagging operation by law enforcement and construction personnel between 7:00 p.m. and
06:00 a.m.
Continue grading for curb and gutter between Woodland Avenue and Central Avenue. Motorists
should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and
Woodland Ave with traffic alternating through the work zone utilizing a flagging operation as
well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection
utilizing a flagging operation by law enforcement and construction personnel between 7:00 p.m.
and 06:00 a.m.
Monday, September 8, 2014 through Friday September 12, 2014
Continue the installation of the privately owned Tidewater Utilities, Inc. water line between
Grants Avenue and Old School Lane. Motorists should anticipate eastbound or westbound lane
closures on Route 26 between Grants Avenue and Old School Lane with traffic alternating through
the work zone utilizing a flagging operation between 7:00 p.m. and 06:00 a.m.