Written on: July 24th, 2014 in Route 26
Sunday July 27, 2014 through Friday August 1, 2014
Begin milling and paving of Central Avenue, south of Route 26. Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation between 8:00 p.m. and 07:00 a.m. as well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 8:00 p.m. and 07:00 a.m.
Continue installation of new drainage system between Woodland Avenue and West Avenue. Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation as well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel on Sunday between 10:30 p.m. and 07:00 a.m. and Monday through Thursday between 8:00 p.m. and 07:00 a.m.
Continue work on the installation of the new drainage system between Cedar Drive and Grants Avenue. Motorists should anticipate the eastbound or westbound lane of Route 26 to be closed between Cedar Drive and Grants Avenue with traffic alternating utilizing a flagging on Sunday between 10:30 p.m. and 07:00 a.m. and Monday through Thursday between 8:00 p.m. and 07:00 a.m.
Sunday August 3, 2014 through Friday August 8, 2014
Begin milling and paving of Central Avenue, north of Route 26. Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation between 8:00 p.m. and 07:00 a.m. as well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel between 8:00 p.m. and 07:00 a.m.
Continue installation of new drainage system between Woodland Avenue and West Avenue. Motorists should anticipate eastbound or westbound lane closures on Route 26 between West Avenue and Woodland Ave with traffic alternating through the work zone utilizing a flagging operation as well as lane closures on Central Avenue at Route 26 with traffic alternating through the intersection utilizing a flagging operation by law enforcement and construction personnel on Sunday between 10:30 p.m. and 07:00 a.m. and Monday through Thursday between 8:00 p.m. and 07:00 a.m.
Continue work on the installation of the new drainage system between Grants Avenue and Old School Lane. Motorists should anticipate the eastbound or westbound lane of Route 26 to be closed between Grants Avenue and Old School Lane with traffic alternating utilizing a flagging on Sunday between 10:30 p.m. and 07:00 a.m. and Monday through Thursday between 8:00 p.m. and 07:00 a.m.