Written on: June 16th, 2011 in I-95 I95/SR1 Interchange
The contractor is continuing to aggressively pursue work on the project. Tasks include excavation for the stormwater management ponds, drainage installation, placing fill material for Ramp G1, and the abutment and wingwalls on the west side of SR 1. The contractor is driving piling for the abutment on the east side of SR 1. Rehabilitation work on the I-95 bridges over SR 1 has started. Work is scheduled to be complete on this project at the end of the year.