Written on: June 16th, 2011 in I-95 I-95 Delaware Toll Plaza
Permanent striping operations continue on the “exit” ends of the toll northbound and southbound plazas. Initial striping of the lengthy north approach to the southbound plaza (one half mile south of the rest area to SR 896) was scheduled for the week of June 13. Acceptance testing for the new tolling systems was scheduled to be complete on Tuesday, June 14. Installation of the remaining overhead signage, final striping, topsoiling, work on the overhead gantry, and punch list items will continue through the end of June. The project is scheduled for completion in August 2011.