SR141/I-95 Ramp Interchange Project

Written on: January 5th, 2017 in SR141

SR141/I-95 Ramp Interchange Project January 3, 2017 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. The contractor will continue to place fill for the widening of SR141 southbound and northbound to I-95. Beam installation will take place on SR141 southbound and the placement of storm drains […]


Read More

SR141/I-95 Ramp Interchange Project

Written on: January 5th, 2017 in SR141

SR141/I-95 Ramp Interchange Project December 23, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. The contractor will continue to place fill for the widening of SR141 southbound and northbound to I-95. Beam installation will take place on SR141 southbound and the placement of storm drains […]


Read More

SR141/I-95 Ramp Interchange Project

Written on: January 5th, 2017 in SR141

SR141/I-95 Ramp Interchange Project December 16, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. The contractor will continue to place fill for the widening of SR141 southbound and northbound to I-95. This week, beam installation will begin on SR141 southbound and the placement of storm […]


Read More

SR141/I-95 Ramp Interchange Project

Written on: December 13th, 2016 in SR141

SR141/I-95 Ramp Interchange Project December 2, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will place fill for the widening of SR141 southbound and northbound to I-95. LANE CLOSURES: Motorists should expect traffic on SR141 northbound and southbound to be reduced […]


Read More

SR141/I-95 Ramp Interchange Project

Written on: December 13th, 2016 in SR141

SR141/I-95 Ramp Interchange Project November 18, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will place fill for the widening of SR141 southbound and northbound to I-95. LANE CLOSURES: Motorists should expect traffic on SR141 northbound and southbound to be reduced […]


Read More

SR141/I-95 Ramp Interchange Project

Written on: November 15th, 2016 in SR141

SR141/I-95 Ramp Interchange Project November 4, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will place fill for the widening of ramps from SR141 southbound to I-95 northbound and constructing the side slopes of southbound SR141. LANE CLOSURES: Motorists should expect […]


Read More

SR141/I95 Ramp Interchange Project

Written on: November 4th, 2016 in SR141

SR141/I-95 Ramp Interchange Project November 4, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will place fill for the widening of ramps from SR141 southbound to I-95 northbound and constructing the side slopes of southbound SR141. LANE CLOSURES: Motorists should expect […]


Read More

SR141/I-95 Ramp Interchange Project

Written on: October 25th, 2016 in SR141

SR141/I-95 Ramp Interchange Project October 21, 2016 The contractor, Mumford & Miller Inc., continues constructing the concrete structures for the new bridges on SR141. This week, the contractor will continue to place fill for the widening of ramps from SR141 northbound and southbound to I-95 northbound and constructing the side slopes of southbound SR141. On […]


Read More

SR141/I-95 Ramp Interchange Project

Written on: October 25th, 2016 in SR141

SR141/I-95 Ramp Interchange Project October 14, 2016 The contractor, Mumford & Miller Inc., has completed driving piles on one side of both southbound and northbound SR141. They are constructing the concrete structures for the new bridges on SR141. This week, the contractor will continue to place fill for the widening of ramps from SR141 northbound […]


Read More

SR141/I-95 Ramp Interchange Project

Written on: October 25th, 2016 in SR141

SR141/I-95 Ramp Interchange Project October 7, 2016 The contractor, Mumford & Miller Inc., has completed driving piles on one side of both southbound and northbound SR141. They are constructing the concrete structures for the new bridges on SR141. This week, the contractor will continue to place fill for the widening of ramps from SR141 northbound […]