Below is an outline of the anticipated construction schedule and associated lane closures for work on the US 301 Mainline Project during the next week.

Written on: April 22nd, 2016 in US 301 Project Updates

Monday, April 25, 2016 through Saturday, April 30, 2016

Continue dirt hauling activities on Hyetts Corner Road. Motorists should anticipate lane closures on Hyetts Corner Road between Airmont Drive and Windsor Commons with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.

Continue work on relocating the ESNG Utility. Motorists should anticipate a lane shift on Summit Bridge Road, north and south of Armstrong Corner Road with both travel lanes getting through the work zone.

Begin excavating for new ditches along Bunker Hill Road in the area of Appoquinimink High school. No lane closures are needed for this construction activity.
Begin dirt hauling activities across Bunker Hill Road. Motorists should anticipate lane closures on Bunker Hill Road near Appoquinimink High School with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 9:00 a.m. to 3:00 p.m.


route-26

Projected construction work for the Route 26 Project

Written on: April 22nd, 2016 in Route 26

Below is an outline of the anticipated construction schedule and associated lane closures for
work on the SR 26 Mainline Improvement Project during the next week.
Monday, April 25, 2016 through Saturday, April 30, 2016
Continue to place concrete for sidewalk on Route 26 between West Avenue and the Assawoman
Canal. Motorists should anticipate eastbound or westbound lane closures on Route 26 between
West Avenue and the Assawoman Canal with traffic alternating through the work zone utilizing
a flagging operation by law enforcement and construction personnel from 9:00 a.m. to 5:00 p.m..
Continue milling and paving on Route 26 at Powell Farm Road. Motorists should anticipate
westbound lane closures on Route 26 at Powell Farm Road with traffic alternating through the
work zone utilizing a flagging operation by law enforcement and construction personnel from
7:00 a.m. to 9:00 a.m..
Monday, April 25, 2016 through Friday, May 13, 2016
Powell Farm Road and Omar Road will be closed at SR 26. Motorists are advised to follow the
following posted detour:
Northbound: Powell Farm Road, right onto Burbage Road, left onto SR 17 and end on SR 26.
Southbound: Powell Farm Road, left on Burbage Road, left on SR 17 and back onto SR 26.





+