Facebook Twitter Flickr YouTube RSS Feed
Written on: June 30th, 2016 in SR141
SR141/I95 Ramp Interchange Project Update
April 22, 2016
The contractor, Mumford and Miller Concrete Inc., is shoring up the west abutments of 141 southbound in preparation for bridge widening over I-95 northbound. Work continues on clearing the slopes also in preparation for the widening. Drainage improvements are being installed between I-95 and I-295 to allow the construction of a temporary cross-over for traffic control purposes.
Beginning April 25th, Delmarva Power Gas will start to work on a temporary relocation of a gas main located on the SR 141 northbound bridge.
LANE CLOSURES:
Motorists should expect traffic on SR 141 northbound and southbound to be reduced to one lane in the construction area during the hours of 9AM to 3PM, Monday thru Friday.
There will be intermittent lane closures on northbound I-95/I-295 from 6PM to 5AM.