Below is an outline of the anticipated construction schedule and associated lane closures for work on the SR 26 Mainline Improvement Project during the next week.

Tuesday, May 31, 2016 through Thursday, June 2, 2016
Continue grading for new curb and placing concrete for new curb on Route 26 at Powell Farm Road. Motorists should anticipate eastbound or westbound shifts on Route 26 at Powell Farm  Road with both lanes getting through the work zone utilizing a flagging operation by construction personnel from 07:00AM to 5:00PM.

Continue adjusting manhole height and paving entrances to driveways and businesses on Route 26 between Old Mill Road and Roxana Road. Motorists should anticipate lane shifts along Route 26 in this corridor with both travel lanes getting through the work zone utilizing a flagging operation by construction personnel from 07:00AM to 5:00PM.

Begin profile milling, wedge and leveling on Route 26 between the Assawoman Canal and Old School Lane. Motorists should anticipate lane shifts along Route 26 in this corridor with both travel lanes getting through the work zone utilizing a flagging operation by construction personnel from 07:00AM to 5:00PM.




+