Written on: February 15th, 2019 in US 301 Project Updates US301
Monday, February 25, 2019, through Friday, March 1, 2019: Dayshift
Continue bridge construction activities on Boyds Corner Road. Motorists should anticipate an eastbound or westbound lane closure on Boyds Corner Road, west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 8:00 AM until 4:00 PM.
Motorists should anticipate a single lane closure on Bunker Hill Road from the bridge over the new US 301 alignment to the roundabout at Chop Tank Road from 9:00 AM until 3:00 PM for curb and gutter construction.
Motorists should anticipate a single lane closure on Summit Bridge Road from Boyd’s Corner Road to Springmill Drive from 8:00 AM until 4:00 PM for excavation and topsoil placement.
Motorists should anticipate a single lane closure on both US 301 Northbound and Southbound from the Maryland State Line to the Delaware Weigh Station from 8:00 AM until 3:00 PM for Stormwater Management Pond construction.
Motorists should anticipate a single left lane closure on either US 301 Northbound and Southbound from the Levels Road Interchange to the Delaware Weigh Station from 7:00 AM until 5:00 PM for the removal of previously used temporary roads.
Monday, February 25, 2019, through Thursday, February 28, 2019: Dayshift
Motorists should expect a single left lane closure on SR 1 Southbound from the Roth Bridge to Biddles Toll Plaza from 9:00 AM until 3:00 PM for median drainage work.
Motorists should expect a left or right lane closure on US 301 Northbound or Southbound from SR 1 to Scotts Run from 9:00 AM until 3:00 PM for erosion and sediment repairs and right of way fence installation.
Motorists should expect a right lane closure on US 13 Southbound from Lorewood Grove Road to Biddles Toll Plaza from 9:00 AM until 3:00 PM for roadside barrier wall grading.
Friday, March 1, 2019: Dayshift
Motorists should expect a right lane closure on US 13 Southbound from Lorewood Grove Road to Biddles Toll Plaza from 7:00AM to 12:00PM for roadside barrier wall grading.
Detours and Roadway Closures
The new US 301 alignment was opened to traffic and tolling on January 10, 2019 from the Maryland State Line to SR 1 in both directions including exits at Jamison Corner Road, the Connector Road to Summit Bridge Road, and Levels Road.
The Stadium/Bus lot and secondary driveway at St. Georges High School is closed to all traffic until further notice except during morning drop off and school dismissal times Monday through Friday. All other vehicles entering/exiting at any other time should use the main entrance to the high school.
Hyetts Corner Road is closed to traffic between the St. Georges High School and Windsor Commons Way. Motorists traveling westbound on Hyetts Corner Road should follow Jamison Corner Road through the roundabout and continue to Boyds Corner Road and turn left, follow Boyds Corner Road to US 13 and turn left, and back to Hyetts Corner Road.
Motorists traveling eastbound on Hyetts Corner Road should turn right at US 13, follow US 13 to Boyds Corner Road, and turn right, follow Boyds Corner Road to Jamison Corner Road and turn right, follow Jamison Corner Road through the roundabout and back to Hyetts Corner Road.