Written on: December 21st, 2018 in US 301 Project Updates US301
Monday, December 24, 2018, Wednesday December 26, 2018, and Thursday December 27, 2018: Dayshift
Continue bridge construction activities on SR 896/Boyds Corner Road. Motorists should anticipate an eastbound or westbound lane closure on SR 896/Boyds Corner Road west of Cedar Lane with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 8 AM until 4 PM.
Motorists should expect single lane closures with flaggers directing traffic in both directions on Jamison Corner Road from Hyetts Corner Road south through the new US 301 interchange from 9 AM until 3 PM.
Motorists should expect single lane closures on Armstrong Corner Road adjacent to Summit Bridge Road with traffic alternating through the work zone utilizing a flagging operation by construction personnel from 8 AM until 4 PM.
Motorists should expect a single lane closure on US 301 in both the northbound and southbound directions near the Maryland state line for roadside construction activities from 8 AM until 3 PM.
Continue bridge construction activities along SR 1. Motorists should anticipate a single left or right lane closure along southbound SR 1 between the Biddles Toll Plaza and the Roth Bridge from 7 AM until 3 PM.
Motorists should anticipate a single left lane closure both northbound and southbound on SR 1 from the Roth Bridge to SR 72 from 9 AM until 3 PM for overhead sign construction.
Continue roadway widening activities along US 13 southbound. Motorists should anticipate a single right lane closure along southbound US 13 between the Free Ramp to SR 1 and Port Penn Road from 7 AM until 2 PM.
Friday, December 28, 2018: Dayshift
Continue roadway widening activities along southbound US 13. Motorists should anticipate a single right lane closure along southbound US 13 between the Free Ramp to SR 1 and Port Penn Road from 7 AM until Noon.
Detours and Roadway Closures
The Stadium/Bus lot and secondary driveway at St. Georges High School is closed to all traffic until further notice except during morning drop off and school dismissal times Monday through Friday. All other vehicles entering/exiting at any other time should use the main entrance to the high school.
Hyetts Corner Road is closed to traffic between the St. Georges High School and Windsor Commons Way. Motorists traveling westbound on Hyetts Corner Road should follow Jamison Corner Road through the roundabout and continue to SR 896/Boyds Corner Road and turn left, follow Boyd’s Corner Road to US 13 and turn left, and back to Hyetts Corner Road.
Motorists traveling eastbound on Hyetts Corner Road should turn right at US 13, follow US 13 to SR 896/Boyds Corner Road and turn right, follow Boyd’s Corner Road to Jamison Corner Road and turn right, follow Jamison Corner Road through the roundabout and back to Hyetts Corner Road.